Challenger App

No.1 PSC Learning App

1M+ Downloads
X, Y and Z can complete a piece of work in 46 days, 92 days and 23 days, respectively. X started the work. Y joined him after 7 days. If Z joined them after 8 days from the beginning, then for how many days did Y work?

A125712\frac{5}{7}

B115711\frac{5}{7}

C105710\frac{5}{7}

D9579\frac{5}{7}

Answer:

115711\frac{5}{7}

Read Explanation:

Solution:

Given data:

Days in which X can complete the work = 46 days

Days in which Y can complete the work = 92 days

Days in which Z can complete the work = 23 days

Days after which Y joined = 7 days

Days after which Z joined = 8 days

Formula used:

Efficiency = Total work / Time taken to complete work individually

Calculation:

LCM of 23, 46, 92 = 92

Assuming that the total work is 92 units.

Efficiency of x-

9246=2\frac{92}{46}=2units of work/day

Efficiency of y-

9292=1\frac{92}{92}=1


Efficiency of z-

9223=4\frac{92}{23}=4

Work done in 7 days by X working alone = 2 units × 7 = 14 units

Work done by X and Y on 8th day =  (2 + 1) × 1 = 3 units

Total work done until 8th day = 14 + 3 = 17 units

Remaining work = 92 - 17 = 75 units

Work done by X , Y and Z in one day = 2 + 1 + 4 = 7 units

Total time taken =757days=\frac{75}{7}days

Total days worked by Y =757+1=827=1157days=\frac{75}{7}+1=\frac{82}{7}=11\frac{5}{7}days


Related Questions:

A 6 ദിവസത്തിൽ ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയുകയും B 9 ദിവസங்களில் സ്ഥിരം ജോലി പൂർത്തിയാക്കാൻ കഴിയുകയും ചെയ്യുന്നു. ഇരുവരും ചേർന്ന് ഈ ജോലിയെ പൂർത്തിയാക്കാൻ എത്ര ദിവസം എടുക്കും?
A & B together do a work in 40 days. B & C together do in 25 days. A and B started working together, and A left work after 6 days & B left work after 8 days. After A left, C join the work & C completed the work in 40.5 days, C alone can complete the work in how many days?
Suresh can complete a job in 15 hours. Ashutosh alone can complete the same job in 10 hours. If Suresh works alone for 9 hours and then stops, how many hours will it take Ashutosh to complete the job alone?
A യ്ക്ക് 15 ദിവസം കൊണ്ടും B യ്ക്ക് 20 ദിവസം കൊണ്ടും ഒരു ജോലി ചെയ്യാൻ കഴിയും. അവർ 4 ദിവസത്തേക്ക് ഒരുമിച്ച് ജോലി ചെയ്യുകയാണെങ്കിൽ, ശേഷിക്കുന്ന ജോലിയുടെ അംശം?
45 ആൾക്കാർ ഒരു ദിവസം 12 മണിക്കൂർ ജോലി ചെയ്ത് 30 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കുമെങ്കിൽ 60 ആൾക്കാർ ഒരു ദിവസം പത്തു മണിക്കൂർ വീതം ജോലി ചെയ്താൽ എത്ര ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാക്കും?