Solution:
Given data:
Days in which X can complete the work = 46 days
Days in which Y can complete the work = 92 days
Days in which Z can complete the work = 23 days
Days after which Y joined = 7 days
Days after which Z joined = 8 days
Formula used:
Efficiency = Total work / Time taken to complete work individually
Calculation:
LCM of 23, 46, 92 = 92
Assuming that the total work is 92 units.
Efficiency of x-
4692=2units of work/day
Efficiency of y-
9292=1
Efficiency of z-
2392=4
Work done in 7 days by X working alone = 2 units × 7 = 14 units
Work done by X and Y on 8th day = (2 + 1) × 1 = 3 units
Total work done until 8th day = 14 + 3 = 17 units
Remaining work = 92 - 17 = 75 units
Work done by X , Y and Z in one day = 2 + 1 + 4 = 7 units
Total time taken =775days
Total days worked by Y =775+1=782=1175days