A's work rate = (121) of the work per day.
B's work rate = (181)of the work per day.
Together, their work rate is:
121+181
=363+2
=365
In the first 4 days, they complete:
4×365=3620=95
Remaining work:
1−95=94
Now A works alone at a rate of (\frac{1}{12}) per day.
Time taken by A to finish the remaining work:
12194
=94×12
=948
=316
=531 days