Challenger App

No.1 PSC Learning App

1M+ Downloads
A and B can complete a task in 12 days and 18 days, respectively. They begin the work together, but B leaves after 4 days. How many more days will A take to finish the remaining work?

A5 1/3 days

B2 3/4 days

C1 1/5 days

D4 3/5 days

Answer:

A. 5 1/3 days

Read Explanation:

A's work rate = (112)(\frac{1}{12}) of the work per day.

B's work rate = (118)(\frac{1}{18}) of the work per day.

Together, their work rate is:


112+118\frac{1}{12}+\frac{1}{18}
=3+236=\frac{3+2}{36}
=536=\frac{5}{36}

In the first 4 days, they complete:


4×536=2036=594 \times \frac{5}{36}=\frac{20}{36}=\frac{5}{9}

Remaining work:


159=491-\frac{5}{9}=\frac{4}{9}

Now A works alone at a rate of (\frac{1}{12}) per day.

Time taken by A to finish the remaining work:


49112\frac{\frac{4}{9}}{\frac{1}{12}}
=49×12=\frac{4}{9}\times 12
=489=\frac{48}{9}
=163=\frac{16}{3}
=513 days=5\tfrac{1}{3}\text{ days}


Related Questions:

10 ആളുകൾക്ക് ഒരു ജോലി ചെയ്യാൻ 8 ദിവസം വേണം. അതേ ജോലി ചെയ്യാൻ 20 ആളുകൾക്ക് എത്ര ദിവസം വേണം ?
A ക്ക് ഒരു ജോലി 6 ദിവസം കൊണ്ടും B ക്ക് 4 ദിവസം കൊണ്ടും ചെയ്യാൻ കഴിയും. രണ്ടുപേരും ഒരുമിച്ച് പ്രവർത്തിച്ചാൽ എത്ര സമയമെടുക്കും?
Anil can do a piece of work in 4 hours. Ashok can do it in 8 hours. With the assistance of Robin, they completed the work in 2 hours. In how many hours can Robin alone do it?
A pipe can fill a tank in 10 hours. Due to a leak in the bottom, it fills the tank in 22.5 hours. If the tank is full, then how much time will the leak take to empty it?
In a company, if 40 workers can make 50 bags in 4 days, then how many bags will 24 workers will make in 8 days ?