Challenger App

No.1 PSC Learning App

1M+ Downloads
A and B can do a job in 10 days and 5 days, respectively. They worked together for two days, after which B was replaced by C and the work was finished in the next three days. How long will C alone take to finish 60% of the job?

A18

B30

C25

D24

Answer:

A. 18

Read Explanation:

Solution: Given: A can do a job in 10 days B can do a job in 5 days Formula used: Efficiency = Total work/Time taken Calculation: LCM of 10 and 5 = 10 = Total work Efficiency of A = 10/10 = 1 unit/day Efficiency of B = 10/5 = 2 units/day A and B work for 2 days ⇒ (1 + 2) × 2 units ⇒ 6 units Remaining work = (10 – 6) units ⇒ 4 units A and C can complete the remaining work in 3 days A and C one day work ⇒ 4/3 C one day work ⇒ (4/3) – 1 ⇒ 1/3 C can complete 60% of work in ⇒ 6 ÷ (1/3) ⇒ 18 days ∴ C can complete 60% of work in 18 days.


Related Questions:

Amit can complete a piece of work in 120 days. Amit and Sejal can complete the same work in 72 days. They started together but Sejal left after working for 20 days. Find the approximate number of days in which Amit will complete the remaining work.
A fort is provisioned for 32 days for some soldiers. After 4 days, a reinforcement of 150 soldiers arrived and the food will now last for 21 days only. How many soldiers were there in the fort in the beginning?
A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take?
A,B എന്നീ രണ്ട് പൈപ്പുകൾക്ക് യഥാക്രമം 15 മിനിറ്റും 20 മിനിറ്റും കൊണ്ട് ഒരു ടാങ്ക് നിറയ്ക്കാനാകും. രണ്ട് പൈപ്പുകളും ഒരുമിച്ച് തുറക്കുന്നു, പക്ഷേ 4 മിനിറ്റിന് ശേഷം പൈപ്പ് A ഓഫ് ചെയ്യുന്നു. ടാങ്ക് നിറയ്ക്കാൻ ആവശ്യമായ ആകെ സമയം എത്രയാണ്?
A fort had provision of food for 150 men for 85 days. After 15 days, 25 men left the fort. Find the number of days for which the remaining food will last.