App Logo

No.1 PSC Learning App

1M+ Downloads
A and B can do a job in 10 days and 5 days, respectively. They worked together for two days, after which B was replaced by C and the work was finished in the next three days. How long will C alone take to finish 60% of the job?

A18

B30

C25

D24

Answer:

A. 18

Read Explanation:

Solution: Given: A can do a job in 10 days B can do a job in 5 days Formula used: Efficiency = Total work/Time taken Calculation: LCM of 10 and 5 = 10 = Total work Efficiency of A = 10/10 = 1 unit/day Efficiency of B = 10/5 = 2 units/day A and B work for 2 days ⇒ (1 + 2) × 2 units ⇒ 6 units Remaining work = (10 – 6) units ⇒ 4 units A and C can complete the remaining work in 3 days A and C one day work ⇒ 4/3 C one day work ⇒ (4/3) – 1 ⇒ 1/3 C can complete 60% of work in ⇒ 6 ÷ (1/3) ⇒ 18 days ∴ C can complete 60% of work in 18 days.


Related Questions:

P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed?
Ramanan and Shyam together can do a work in 8 days. Both of B them began to work. After 3 days Ramanan fell ill, Shyam completed the remaining work in 15 days. In how many days can Ramanan complete the work?
A and B can separately do a piece of work in 6 days and 12 days respectively. How long will they together take to do the work ?
Jitesh and Kamal can complete a certain piece of work in 7 and 16 days, respectively, They started to work together, and after 2 days, Kamal left. In how many days will Jitesh complete the remaining work?
A and B can do a work together in 18 days. A is three times as efficient as B. In how many days can B alone complete the work?