App Logo

No.1 PSC Learning App

1M+ Downloads
A and B can do a job in 10 days and 5 days, respectively. They worked together for two days, after which B was replaced by C and the work was finished in the next three days. How long will C alone take to finish 60% of the job?

A18

B30

C25

D24

Answer:

A. 18

Read Explanation:

Solution: Given: A can do a job in 10 days B can do a job in 5 days Formula used: Efficiency = Total work/Time taken Calculation: LCM of 10 and 5 = 10 = Total work Efficiency of A = 10/10 = 1 unit/day Efficiency of B = 10/5 = 2 units/day A and B work for 2 days ⇒ (1 + 2) × 2 units ⇒ 6 units Remaining work = (10 – 6) units ⇒ 4 units A and C can complete the remaining work in 3 days A and C one day work ⇒ 4/3 C one day work ⇒ (4/3) – 1 ⇒ 1/3 C can complete 60% of work in ⇒ 6 ÷ (1/3) ⇒ 18 days ∴ C can complete 60% of work in 18 days.


Related Questions:

Two pipes A and B can fill a cistern in 36 minutes and 48 minutes, respectively. Both the pipes are opened at the same time and pipe B is closed after some time. If the cistern gets filled in half an hour, then after how many minutes was pipe B closed?
15 പേർ 24 ദിവസം കൊണ്ട് ചെയ്ത് തീർക്കുന്ന ജോലി 18 ദിവസം കൊണ്ട് തീർക്കാൻ എത്ര പേർ വേണം?
എ,ബി എന്നി ടാപ്പുകൾക്ക് യഥാക്രമം 6 മണിക്കൂറും 10 മണിക്കൂറും കൊണ്ട് ഒരു ടാങ്ക് നിറയ്ക്കുവാൻ കഴിയും .എന്നാൽ ടാങ്കിലെ C എന്നദ്വാരം 8 മണിക്കൂർ സമയം കൊണ്ട് നിറഞ്ഞ ടാങ്കിനെ ശൂന്യമാകും.ഒഴിഞ്ഞ ടാങ്കിൽ ദ്വാരം C തുറന്ന് കിടക്കുമ്പോൾ 2 ടാപ്പുകളും ഒരുമിച്ച് തുറന്നാൽ എത്ര സമയം കൊണ്ട് ടാങ്ക് നിറയും ?
6/7 part of a tank is filled with oil. After taking out 60 litres of oil the tank is 4/5 part full. What is the capacity (in litres) of the tank?
Surbhi can do a piece of work in 24 days. She completed 3/8 of the work and then left it. Amit can complete the remaining work in 10 days. Working together, they will complete 125% of the same work in: