App Logo

No.1 PSC Learning App

1M+ Downloads
A and B can do a job in 10 days and 5 days, respectively. They worked together for two days, after which B was replaced by C and the work was finished in the next three days. How long will C alone take to finish 60% of the job?

A18

B30

C25

D24

Answer:

A. 18

Read Explanation:

Solution: Given: A can do a job in 10 days B can do a job in 5 days Formula used: Efficiency = Total work/Time taken Calculation: LCM of 10 and 5 = 10 = Total work Efficiency of A = 10/10 = 1 unit/day Efficiency of B = 10/5 = 2 units/day A and B work for 2 days ⇒ (1 + 2) × 2 units ⇒ 6 units Remaining work = (10 – 6) units ⇒ 4 units A and C can complete the remaining work in 3 days A and C one day work ⇒ 4/3 C one day work ⇒ (4/3) – 1 ⇒ 1/3 C can complete 60% of work in ⇒ 6 ÷ (1/3) ⇒ 18 days ∴ C can complete 60% of work in 18 days.


Related Questions:

If 16 men or 20 women can do a piece of work in 25 days. In what time will 28 men and 15 women do it?
A, B and C contract to do a work for Rs. 4200. A can do the work in 6 days, B in 10 days and C in 12 days. If they work together to do the work, what is the share of C (in Rs.)?
A, B, and C can do a piece of work in 42, 56, and 63 days respectively. They started the work together but A left the work 10 days before the completion of the work while B left the work 12 days before the completion. Find the number of days (approximate) to complete the whole work.
8 പേർ 6 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി 3 പേർ എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും?
A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in