App Logo

No.1 PSC Learning App

1M+ Downloads
25 men can complete a task in 16 days. Four days after they started working, 5 more men, with equal workmanship, joined them. How many days will be needed by all to complete the remaining task?

A15 days

B18 days

C12 days

D10 days

Answer:

D. 10 days

Read Explanation:

Solution: Given: 25 men do the task in 16 days 5 more men had joined them Formula Used: If M1 men can finish W1 work in D1 days and M2 men can finish W2 work in D2 days then, (M1 × D1)/W1 = (M2 × D2)/W2 Calculation: Total work done by 25 men = 25 × 16 = 400 units Work done in 1st four days = 25 × 4 = 100 units Remaining work = 400 - 100 = 300 units Numbers of men joined = 5 Total number of men = 25 + 5 = 30 Remaining work done by 30 men in x days 300 = 30 × x x = 10 ∴ 10 days will be needed by all to complete the remaining task


Related Questions:

A, B എന്നിവർക്ക് 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. B, C എന്നിവർക്ക് 15 ദിവസം കൊണ്ട് അതേ ജോലി പൂർത്തിയാക്കാൻ കഴിയും. C, A എന്നിവർക്ക് 20 ദിവസം കൊണ്ട് അതേ ജോലി പൂർത്തിയാക്കാൻ കഴിയും. A, B, C എന്നിവർ ഒരുമിച്ച് പ്രവർത്തിക്കുന്നുവെങ്കിൽ, എത്ര ദിവസം കൊണ്ട് അതേ ജോലി പൂർത്തിയാക്കാൻ കഴിയും?
A, B and C complete a piece of work in 20, 9 and 12 days respectively. Working together, they will complete the same work in
12 ആളുകൾ ചേർന്ന് ഒരു ജോലി 15 ദിവസംകൊണ്ട് തീർക്കും. എന്നാൽ അതേ ജോലി 10 ആളുകൾ എത്ര ദിവസം കൊണ്ട് തീർക്കും?
ഒരു നിശ്ചിത ദൂരം പിന്നിടാൻ എടുക്കുന്ന സമയം 20 % കുറക്കാൻ ഒരു ഓട്ടക്കാരൻ തന്റെ വേഗത എത്ര ശതമാനം വർധിപ്പിക്കണം ?
ഒരു ജോലി A-യ്ക്ക് 5 ദിവസം കൊണ്ടും B-യ്ക്ക് 20 ദിവസം കൊണ്ടും തീർക്കാൻ കഴിയും. അതേ ജോലി A-യും B-യുംകൂടി ഒരുമിച്ച് ചെയ്താൽ എത ദിവസംകൊണ്ട് തീർക്കാൻ കഴിയും?