Challenger App

No.1 PSC Learning App

1M+ Downloads
25 men can complete a task in 16 days. Four days after they started working, 5 more men, with equal workmanship, joined them. How many days will be needed by all to complete the remaining task?

A15 days

B18 days

C12 days

D10 days

Answer:

D. 10 days

Read Explanation:

Solution: Given: 25 men do the task in 16 days 5 more men had joined them Formula Used: If M1 men can finish W1 work in D1 days and M2 men can finish W2 work in D2 days then, (M1 × D1)/W1 = (M2 × D2)/W2 Calculation: Total work done by 25 men = 25 × 16 = 400 units Work done in 1st four days = 25 × 4 = 100 units Remaining work = 400 - 100 = 300 units Numbers of men joined = 5 Total number of men = 25 + 5 = 30 Remaining work done by 30 men in x days 300 = 30 × x x = 10 ∴ 10 days will be needed by all to complete the remaining task


Related Questions:

6 മിനിട്ടുകൊണ്ട് ഒരു ടാങ്കിന്റെ 3/5 ഭാഗം നിറഞ്ഞു. ഇനി നിറയാൻ എത്ര മിനിട്ടു വേണം ?
മൂന്നു സംഖ്യകളുടെ അനുപാതം 3:5 :7 ആണ്.ആദ്യത്തെ സംഖ്യയും മൂന്നാമത്തെ സംഖ്യയും കൂട്ടിയാൽ രണ്ടാമത്തെ സംഖ്യയേക്കാൾ 40 കൂടുതലാണെങ്കിൽ ,ഏറ്റവും വലിയ സംഖ്യ എത്ര ?
A and B working separately can finish a work in 15 days and 20 days. respectively. If they work on alternate days. A starting first, and if the work goes on for 8 days, what part of the work will be left unfinished?
അജിത്തും സൽമാനും ഒരു ജോലിയുടെ 20% ആദ്യ 3 ദിവസം ചെയ്യുന്നു. പിന്നീട് ചില ശാരീരിക പ്രശ്‌നങ്ങൾ കാരണം അജിത്ത് ജോലി നിർത്തി പോകുന്നു . പിന്നെ സൽമാൻ മാത്രം ബാക്കിയുള്ള ജോലികൾ 20 ദിവസം കൊണ്ട് തീർക്കുന്നു. മുഴുവൻ ജോലിയും ചെയ്യാൻ അജിത്ത് മാത്രം എത്ര ദിവസം എടുക്കും?
Pipe P can fill 4/9 part of a tank in 28 hours and pipe Q can fill 3/5 part of the same tank in 27 hours. Both P and Q were kept open for 3 hours, then both were closed. Pipe R alone was then opened and it emptied the water in the tank in 8 hours. Pipes P, Q and R together can fill the empty tank in: