App Logo

No.1 PSC Learning App

1M+ Downloads
25 men can complete a task in 16 days. Four days after they started working, 5 more men, with equal workmanship, joined them. How many days will be needed by all to complete the remaining task?

A15 days

B18 days

C12 days

D10 days

Answer:

D. 10 days

Read Explanation:

Solution: Given: 25 men do the task in 16 days 5 more men had joined them Formula Used: If M1 men can finish W1 work in D1 days and M2 men can finish W2 work in D2 days then, (M1 × D1)/W1 = (M2 × D2)/W2 Calculation: Total work done by 25 men = 25 × 16 = 400 units Work done in 1st four days = 25 × 4 = 100 units Remaining work = 400 - 100 = 300 units Numbers of men joined = 5 Total number of men = 25 + 5 = 30 Remaining work done by 30 men in x days 300 = 30 × x x = 10 ∴ 10 days will be needed by all to complete the remaining task


Related Questions:

6 ആളുകൾ ഒരു ജോലി 10 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്നു . എന്നാൽ ഒരാൾ ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?
A can finish painting a sari in 11 days, B in 20 days and C in 55 days, if they work independently. In how many days can the work be completed if A is assisted by B on every odd numbered day and by C on every even numbered day till the work completes?
If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 men do the same work by working 6 hours a day?
A man running at a speed of 15 km/hr crosses a bridge in 3 minutes. What is the length of the bridge?
A and B together can complete a work in 8 days. B alone can complete the work in 24 days. In how many days A alone can complete the same work?