Challenger App

No.1 PSC Learning App

1M+ Downloads
A and B can do a piece of work in 28 days and 35 days, respectively. They work on alternate days starting with A till the work gets completed. How long (in days) would it take A and B to complete the work?

A311531\frac15

B311231\frac12

C3131

D311931\frac19

Answer:

3131

Read Explanation:

A can do the work in =28=28

B can do the work in =35=35

LCM of this two is the total work = 140

efficiency of A =140/28=5= 140/28=5

efficiency of B =140/35=4= 140/35=4

straiting A alternate with B the two day work is = 9

140/9=15140/9=15 and reminder 5

days =15×2=30=15\times 2=30

one day work is done by A

30+1=3130+1=31


Related Questions:

20 women can complete a work in 15 days. 16 men can complete the same work in 15 days. Find the ratio between the work efficiency of a man to a woman.
A യും B യും ഒരു ജോലി 72 ദിവസത്തിൽ പൂർത്തിയാക്കും. B യും C യും ചേർന്ന് അതേ ജോലി 120 ദിവസത്തിൽ പൂർത്തിയാക്കും. A യും C യും ചേർന്ന് അത് 90 ദിവസത്തിൽ പൂർത്തിയാക്കും. എന്നാൽ A, B,C മൂന്നുപേരും ഒരുമിച്ച് ജോലി ചെയ്താൽ 3 ദിവസത്തിൽ അവർ എത്ര ഭാഗം ജോലി പൂർത്തിയാക്കും?
A and B can do a work in 30 days and 10 days respectively. If they work on alternate days starting with A, then in how many days will the work be completed ?
ഒരാൾ ഒരു ദിവസം കൊണ്ട് 2 മീറ്റർ × 2 മീറ്റർ × 2 മീറ്റർ സൈസിൽ ഒരു കുഴി നിർമ്മിക്കും. ഇതേ നിരക്കിൽ 3 പേർ ചേർന്ന് 4 മീറ്റർ × 4 മീറ്റർ × 4 മീറ്റർ സൈസിൽ ഒരു കുഴി നിർമ്മിക്കാൻ എത്ര ദിവസം വേണം?
A സ്കൂൾ പദ്ധതി 20 ദിവസം കൊണ്ട് പൂർത്തിയാക്കി. A-യെക്കാൾ 25% കൂടുതൽ കാര്യക്ഷമതയുണ്ടെങ്കിൽ B ഇതേ ജോലി പൂർത്തിയാക്കാൻ എത്ര ദിവസമെടുക്കും?