App Logo

No.1 PSC Learning App

1M+ Downloads
A and B can do a piece of work in 28 days and 35 days, respectively. They work on alternate days starting with A till the work gets completed. How long (in days) would it take A and B to complete the work?

A311531\frac15

B311231\frac12

C3131

D311931\frac19

Answer:

3131

Read Explanation:

A can do the work in =28=28

B can do the work in =35=35

LCM of this two is the total work = 140

efficiency of A =140/28=5= 140/28=5

efficiency of B =140/35=4= 140/35=4

straiting A alternate with B the two day work is = 9

140/9=15140/9=15 and reminder 5

days =15×2=30=15\times 2=30

one day work is done by A

30+1=3130+1=31


Related Questions:

10 ആളുകൾക്ക് ഒരു ജോലി ചെയ്യാൻ 8 ദിവസം വേണം. അതേ ജോലി ചെയ്യാൻ 20 ആളുകൾക്ക് എത്ര ദിവസം വേണം ?
E and F can do a work in 10 days. If E alone can do it in 30 days, F alone can do it in ____ days.
8 men and 12 women finish a job in 4 days. While 6 men and 14 women in 5 days. In how many days will 20 women finish the job?
Ganesh, Ram and Sohan together can complete a work in 16 days. If Ganesh and Ram together can complete the same work in 24 days, the number of days Sohan alone takes, to finish the work is
A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?