Challenger App

No.1 PSC Learning App

1M+ Downloads
A and B can do a piece of work in 28 days and 35 days, respectively. They work on alternate days starting with A till the work gets completed. How long (in days) would it take A and B to complete the work?

A311531\frac15

B311231\frac12

C3131

D311931\frac19

Answer:

3131

Read Explanation:

A can do the work in =28=28

B can do the work in =35=35

LCM of this two is the total work = 140

efficiency of A =140/28=5= 140/28=5

efficiency of B =140/35=4= 140/35=4

straiting A alternate with B the two day work is = 9

140/9=15140/9=15 and reminder 5

days =15×2=30=15\times 2=30

one day work is done by A

30+1=3130+1=31


Related Questions:

Ravi can complete one-fourth of the total work in 15 days, Chavi can complete one-third of the total work in 18 days, Dhani can complete half of the total work in 24 days. In how much time can Ravi, Chavi and Dhani complete three-fourth of the work together?
ഒരു ജോലി 8 പുരുഷന്മാരോ 12 സ്ത്രീകളോ 25 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ കഴിയുമെങ്കിൽ ,10 പുരുഷന്മാരും 5 സ്ത്രീകളും എത്ര ദിവസത്തിനുള്ളിൽ അതേ ജോലി പൂർത്തിയാക്കും ?
Two pipes can fill a tank in 30 hours and 40 hours, respectively. Find the time (in hours) taken to fill the tank when both the pipes are opened simultaneously.
Kiran can do a certain piece of work in 15 days. Kiran and Garima can together do the same work in 10 days, and Kiran, Garima and Mehak can do the same work together in 9 days. In how many days can Kiran and Mehak do the same work?
Pravin can do a piece of work in 6 hours. Rishi can do it in 28 hours. With the assistance of Shan, they completed the work in 4 hours. In how many hours can Shan alone do it?