App Logo

No.1 PSC Learning App

1M+ Downloads
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work?

A4 days

B6 days

C8 days

D10 days

Answer:

B. 6 days

Read Explanation:

Let, B alone can complete the work in be x days

According to the question,

112+1x=14\frac{1}{12}+\frac{1}{x} = \frac{1}{4}

1x=14112\frac{1}{x} =\frac{1}{4}-\frac{1}{12}

1x=(31)12\frac{1}{x} = \frac{(3-1)}{12}

1x=16\frac{1}{x} =\frac{1}{6}

⇒ x = 6

∴ B alone can complete the work in 6 days

Alternate Solution

Let total work done be 12 units (LCM of 4 and 12)

Hence,

Efficiency of A + B = 124=3units/day\frac{12}{4} = 3 units/day

Efficiency of A = 1212=1unit/day\frac{12}{12} = 1 unit/day

Now, efficiency of B = 3 - 1 = 2 units/day

∴ Required days = Total work/Efficiency of B = 122=6days\frac{12}{2} = 6 days


Related Questions:

രാജു ഒരു ജോലി 20 ദിവസം കൊണ്ട് ചെയ്ത് തീർക്കും. ഗോപു അതേ ജോലി ചെയ്യാൻ 30 ദിവസം എടുക്കും. എങ്കിൽ രണ്ടുപേരും ചേർന്നാൽ ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?
40 പേർ ഒരു ദിവസം 10 മണിക്കൂർ ജോലി ചെയ്‌താൽ ഒരു ജോലി 12 ദിവസം കൊണ്ട് തീർക്കാൻ ആകും. ഇതേ ജോലി ഒരാൾ ഒരു ദിവസം 11 മണിക്കൂർ ചെയ്‌ത 16 ദിവസം കൊണ്ട് തീർക്കണമെങ്കിൽ എത്ര പേരെ ഒഴിവാക്കണം?
How many men will be required to plough 50 acres of land in 10 days if 15 men are required 6 days to plough 10 acres of land?
6 പുരുഷന്മാർക്കും 7 സ്ത്രീകൾക്കും 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും 2 പുരുഷന്മാർക്കും 5 സ്ത്രീകൾക്കും 20 ദിവസംകൊണ്ട് ആ ജോലി പൂർത്തിയാക്കാൻ കഴിയും എങ്കിൽ 10 പുരുഷന്മാർക്ക് എത്ര ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാക്കാൻ കഴിയും
A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :