App Logo

No.1 PSC Learning App

1M+ Downloads
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work?

A4 days

B6 days

C8 days

D10 days

Answer:

B. 6 days

Read Explanation:

Let, B alone can complete the work in be x days

According to the question,

112+1x=14\frac{1}{12}+\frac{1}{x} = \frac{1}{4}

1x=14112\frac{1}{x} =\frac{1}{4}-\frac{1}{12}

1x=(31)12\frac{1}{x} = \frac{(3-1)}{12}

1x=16\frac{1}{x} =\frac{1}{6}

⇒ x = 6

∴ B alone can complete the work in 6 days

Alternate Solution

Let total work done be 12 units (LCM of 4 and 12)

Hence,

Efficiency of A + B = 124=3units/day\frac{12}{4} = 3 units/day

Efficiency of A = 1212=1unit/day\frac{12}{12} = 1 unit/day

Now, efficiency of B = 3 - 1 = 2 units/day

∴ Required days = Total work/Efficiency of B = 122=6days\frac{12}{2} = 6 days


Related Questions:

'A' യും 'B' യും കൂടി 18 ദിവസങ്ങൾ കൊണ്ട് തീർക്കുന്ന ഒരു ജോലി 'B' യും 'C' യും കൂടി 24 ദിവസങ്ങൾ കൊണ്ടും 'A' യും 'C' യും കൂടി 36 ദിവസങ്ങൾ കൊണ്ടുംതീർക്കും. എങ്കിൽ, 'C' ഒറ്റയ്ക്ക് ഈ ജോലി തീർക്കാൻ എത്ര ദിവസങ്ങൾ എടുക്കും?
P, Q, R എന്നിവയ്ക്ക് യഥാക്രമം 8, 16, 24 ദിവസങ്ങളിൽ ഒരു ജോലി ചെയ്യാൻ കഴിയും. എല്ലാവരും ഒരുമിച്ച് ജോലി ആരംഭിച്ചു P മാത്രം ജോലി പൂർത്തിയാകുന്നത് വരെ തുടർന്നു, ആരംഭിച്ചു രണ്ടു ദിവസത്തിനുശേഷം R ഉം ജോലിപൂർത്തിയാകുന്നതിന് ഒരു ദിവസം മുൻപ് Q ഉം പിരിഞ്ഞു പോയി എങ്കിൽ ജോലി പൂർത്തിയാക്കാൻ എടുക്കുന്ന സമയം
രമ ഒരു ജോലി 12 ദിവസം കൊണ്ട് തീർക്കും. രമണി അതേ ജോലി 18 ദിവസം കൊണ്ട് തീർക്കും. രാജുവും രമയും രമണിയും കൂടി ഈ ജോലി 4 ദിവസം കൊണ്ട് തീർക്കും. എന്നാൽ രാജുവിന് ഈ ജോലി തീർക്കാൻ എത്ര ദിവസം വേണം ?
A ക്കും B ക്കും നാലുദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും A മാത്രം 12 ദിവസം കൊണ്ട് ഈ ജോലി പൂർത്തിയാക്കും B മാത്രം എത്ര ദിവസം കൊണ്ട് ഈ ജോലി പൂർത്തിയാക്കാൻ സാധിക്കും
48 ആളുകൾ 14 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ജോലി 12 ദിവസം കൊണ്ട് തീർക്കണമെങ്കിൽ എത്ര പേരെ കൂടുതലായി നിയമിക്കണം?