Let, B alone can complete the work in be x days
According to the question,
121+x1=41
⇒ x1=41−121
⇒ x1=12(3−1)
⇒ x1=61
⇒ x = 6
∴ B alone can complete the work in 6 days
Alternate Solution
Let total work done be 12 units (LCM of 4 and 12)
Hence,
Efficiency of A + B = 412=3units/day
Efficiency of A = 1212=1unit/day
Now, efficiency of B = 3 - 1 = 2 units/day
∴ Required days = Total work/Efficiency of B = 212=6days