App Logo

No.1 PSC Learning App

1M+ Downloads
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work?

A4 days

B6 days

C8 days

D10 days

Answer:

B. 6 days

Read Explanation:

Let, B alone can complete the work in be x days

According to the question,

112+1x=14\frac{1}{12}+\frac{1}{x} = \frac{1}{4}

1x=14112\frac{1}{x} =\frac{1}{4}-\frac{1}{12}

1x=(31)12\frac{1}{x} = \frac{(3-1)}{12}

1x=16\frac{1}{x} =\frac{1}{6}

⇒ x = 6

∴ B alone can complete the work in 6 days

Alternate Solution

Let total work done be 12 units (LCM of 4 and 12)

Hence,

Efficiency of A + B = 124=3units/day\frac{12}{4} = 3 units/day

Efficiency of A = 1212=1unit/day\frac{12}{12} = 1 unit/day

Now, efficiency of B = 3 - 1 = 2 units/day

∴ Required days = Total work/Efficiency of B = 122=6days\frac{12}{2} = 6 days


Related Questions:

P യും Q വും ചേർന്ന് 12 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാൻ കഴിയും, P ക്ക് മാത്രം 15 ദിവസം കൊണ്ട് ചെയ്യാൻ കഴിയും. Q മാത്രം എത്ര ദിവസത്തിനുള്ളിൽ അത് ചെയ്യാൻ കഴിയും?
ഒരാൾ 20 ദിവസംകൊണ്ട് ഒരു ജോലി ചെയ്തുതീർക്കും. 12 ദിവസംകൊണ്ട് ആ ജോലിയുടെ എത്ര ശതമാനം തീർക്കും?
30 men working 8 hours per day can dig a pond in 16 days. By working how many hours per day can 32 men dig the same pond in 20 days?
16 ആളുകൾ 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കും. ഈ ജോലി 8 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ എത്ര ആളുകൾ കൂടുതലായി വേണം ?

A can do 331333\frac{1}{3}% of a work in 10 days and B can do 662366\frac{2}{3}% of the same work in 8 days. Both together worked for 8 days then C alone completes the remaining work in 3 days. A and C together will complete 56\frac{5}{6} part of the original work in: