App Logo

No.1 PSC Learning App

1M+ Downloads
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work?

A4 days

B6 days

C8 days

D10 days

Answer:

B. 6 days

Read Explanation:

Let, B alone can complete the work in be x days

According to the question,

112+1x=14\frac{1}{12}+\frac{1}{x} = \frac{1}{4}

1x=14112\frac{1}{x} =\frac{1}{4}-\frac{1}{12}

1x=(31)12\frac{1}{x} = \frac{(3-1)}{12}

1x=16\frac{1}{x} =\frac{1}{6}

⇒ x = 6

∴ B alone can complete the work in 6 days

Alternate Solution

Let total work done be 12 units (LCM of 4 and 12)

Hence,

Efficiency of A + B = 124=3units/day\frac{12}{4} = 3 units/day

Efficiency of A = 1212=1unit/day\frac{12}{12} = 1 unit/day

Now, efficiency of B = 3 - 1 = 2 units/day

∴ Required days = Total work/Efficiency of B = 122=6days\frac{12}{2} = 6 days


Related Questions:

Six typists can type a given data in 16 days. How many days will 4 typists take to do the same work?
Two pipes A and B can fill a tank in 6 hours and 8 hours respectivley. If both the pipes are opened together, then after how many hours should B be closed so that the tank is full in 4 hours ?
ഒരു ടാങ്കിൻറ നിർഗമന കുഴൽ തുറന്നാൽ 2 മണിക്കൂർ കൊണ്ട് നിറയും. ബഹിർഗമന കുഴൽ തുറന്നാൽ 3 മണിക്കൂർ കൊണ്ട് ടാങ്ക് കാലിയാവും. രണ്ട് കുഴലുകളും ഒരുമിച്ച് തുറന്നാൽ എത്ര സമയം കൊണ്ട് ടാങ്ക് നിറയും?
തോമസ് കമ്പിവേലി കെട്ടാൻ വേണ്ടി ഒരാളെ ഏർപ്പെടുത്തി. ഉച്ചയായപ്പോൾ 1/3 ഭാഗം പണി കഴിഞ്ഞു. വൈകുന്നേരമായപ്പോൾ ബാക്കിയുള്ളതിൻറെ പകുതി ഭാഗവും തീർത്തു. ഇനി എത്ര ഭാഗം ബാക്കിയുണ്ട്?
30 പേർ ചേർന്ന് 8 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി 40 പേർ ചേർന്ന് എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?