A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days A finished the remaining work. In how many days A alone can finish the job?
A50
B60
C48
D54
Answer:
B. 60
Read Explanation:
(A+B)'s one day work=1/30
(A+B)'s 20 days work=20/30=2/3
Remaining work=1-2/3=1/3
Now 1/3 part of work is done by A in 20 days. Whole work will be done by A alone is 20 x 3 = 60 days