A and B together can complete a work in 12 days. B and C together can complete the same work in 15 days. C and A together can do it in 20 days. In how many days can A alone complete the job ?

A30 days

B20 days

C50 days

D15 days

Answer:

A. 30 days

Read Explanation:

Let the one-day work rates of A, B, and C be (a), (b), and (c).

Given:

a+b=112a+b=\frac{1}{12}
b+c=115b+c=\frac{1}{15}
c+a=120c+a=\frac{1}{20}

Add all three equations:

2(a+b+c)=112+115+1202(a+b+c)=\frac{1}{12}+\frac{1}{15}+\frac{1}{20}

Take LCM (=60):

2(a+b+c)=5+4+360=1260=152(a+b+c)=\frac{5+4+3}{60}=\frac{12}{60}=\frac{1}{5}
a+b+c=110a+b+c=\frac{1}{10}

Now find (a):

a=(a+b+c)(b+c)a=(a+b+c)-(b+c)
a=110115a=\frac{1}{10}-\frac{1}{15}


=3230=130=\frac{3-2}{30}=\frac{1}{30}

So A alone can complete the work in:

30 days\boxed{30 \text{ days}}


Related Questions:

A യ്ക്ക് കെട്ടിടത്തിന്റെ ബേസ്‌മെന്റ് 20 ദിവസം കൊണ്ട് നിർമ്മിക്കാൻ കഴിയും. B യ്ക്ക് അതേ ജോലി 30 ദിവസം കൊണ്ടും C യ്ക്ക് ആ ജോലി 60 ദിവസം കൊണ്ടും ചെയ്യാൻ കഴിയും. A, B, C എന്നിവർ ഒരുമിച്ച് പ്രവർത്തിച്ചാൽ ബേസ്‌മെന്റ് നിർമ്മിക്കാൻ എത്ര ദിവസം വേണം?

In a company, if 40 workers can make 50 bags in 4 days, then how many bags will 24 workers will make in 8 days ?
A, B and C can complete a piece of work in 12, 20 and 15 days, respectively. A, B and C will complete the work while working on alternate days. C works on the 1st day, B works on the 2nd day and A works on the 3rd day and so on. In how many days will the work get complete?
A car covers 40% of a certain distance at a pace of 20 km/h and the remaining distance at a pace of 30 km/h. What is the average speed of the car for the entire journey?
A pipe can fill a tank in 10 hours. Due to a leak in the bottom, it fills the tank in 22.5 hours. If the tank is full, then how much time will the leak take to empty it?