Challenger App

No.1 PSC Learning App

1M+ Downloads
A and B together can complete a work in 8 days. B alone can complete the work in 24 days. In how many days A alone can complete the same work?

A16

B14

C12

D13

Answer:

C. 12


Related Questions:

A, B, C can together complete the work in 12 days. If A is thrice faster than B, and B is twice faster than C , B alone can do the work in :
Two pipes A and B can fill a cistern in 36 minutes and 48 minutes, respectively. Both the pipes are opened at the same time and pipe B is closed after some time. If the cistern gets filled in half an hour, then after how many minutes was pipe B closed?
P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed?
Two pipes can fill a cistern separately in 10 hours and 15 hours. They can together fill the cistern in
There are three pipes A, B, C in a tank. If all the three pipes are open together the tank will be filled in 15 minutes. A and C are open together the tank will be fill in 20 minutes if B alone is open the tank will be filled in how many minutes ?