Work done per day:
A’s one day work (=301)
B’s one day work (=451)
C’s one day work (=901)
On every 5th day, all three work together.
Work done by A alone for 4 days:
Work done on the 5th day by A, B, and C together:
301+451+901
LCM(=90)
=903+2+1=906=151
Total work in 5 days:
So,(51) of the work is completed every 5 days.
Hence total time:
5×5=25 days
Therefore, the task will be completed in 25 days.