A, B, and C are capable of completing a job in 30, 45, and 90 days, respectively. A works every day, while B and C join A every fifth day. How long will it take to finish the task?

A25 days

B18 days

C13 days

D17 days

Answer:

A. 25 days

Read Explanation:

Work done per day:

  • A’s one day work (=130)(= \frac{1}{30})

  • B’s one day work (=145)(= \frac{1}{45})

  • C’s one day work (=190)(= \frac{1}{90})

On every 5th day, all three work together.

Work done by A alone for 4 days:

  • 4×130=2154\times\frac{1}{30}=\frac{2}{15}

Work done on the 5th day by A, B, and C together:

130+145+190\frac{1}{30}+\frac{1}{45}+\frac{1}{90}

LCM(=90)LCM (= 90)


=3+2+190=690=115=\frac{3+2+1}{90}=\frac{6}{90}=\frac{1}{15}

Total work in 5 days:

  • 215+115=315=15\frac{2}{15}+\frac{1}{15}=\frac{3}{15}=\frac{1}{5}

So,(15) (\frac{1}{5}) of the work is completed every 5 days.

Hence total time:

5×5=25 days5 \times 5 = 25 \text{ days}

Therefore, the task will be completed in 25 days.


Related Questions:

ഒരു ജോലി 8 പുരുഷന്മാരോ 12 സ്ത്രീകളോ 25 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ കഴിയുമെങ്കിൽ ,10 പുരുഷന്മാരും 5 സ്ത്രീകളും എത്ര ദിവസത്തിനുള്ളിൽ അതേ ജോലി പൂർത്തിയാക്കും ?
ഒരു പരീക്ഷ തുടങ്ങാനായി ഒരു ബെല്ലടിക്കുകയും തുടർന്ന് ഓരോ അരമണിക്കൂർ കഴിയുമ്പോഴും ഓരോ ബെല്ലടിക്കുകയും ചെയ്യുന്നു. ആകെ 6 ബെല്ലടിച്ചുവെങ്കിൽ പരീക്ഷ സമയം എത്ര ?
24 പുരുഷന്മാർക്ക് ഒരു ജോലി 10 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാമെങ്കിൽ 30പേർക്ക് എത്ര ദിവസം വേണ്ടി വരും?
The ratio of efficiencies of 2 workers , P and Q is 5:2. If P can complete a project in 12 days, how many days will Q take to complete the same project alone ?
20 ആളുകൾ 30 ദിവസം കൊണ്ട് ചെയ്യുന്ന ഒരു ജോലി 25 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കണമെങ്കിൽ ഇനി എത്ര ആളുകൾ കൂടി വേണം?