The ratio of efficiencies of 2 workers , P and Q is 5:2. If P can complete a project in 12 days, how many days will Q take to complete the same project alone ?

A24 days

B30 days

C40 days

D35 days

Answer:

B. 30 days

Read Explanation:

Q will take 30 days to complete the project alone.

  • Efficiency Ratio: P : Q = 5:25 : 2

  • Work Formula: Total Work=Efficiency×Time\text{Total Work} = \text{Efficiency} \times \text{Time}

  • Calculate Total Work: 5×12 days=60 units5 \times 12\text{ days} = 60\text{ units}

  • Calculate Q's Time: 60 units÷2=30 days60\text{ units} \div 2 = 30\text{ days}


Related Questions:

A shopkeeper mixes two qualities of tea. The first quality costs ₹150 per kg and is mixed with the second quality in the ratio 4: 5. If the mixture is sold at ₹130 per kg (at no profit, no loss), what is the cost per kg of the second quality of tea?
X ഒരു ജോലിയുടെ 1/4 ഭാഗം 10 ദിവസം കൊണ്ട് പൂർത്തിയാക്കും , Y ന് 40% ജോലി 40 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാനും , Z ന് ജോലിയുടെ 1/3 ഭാഗം 13 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാനും കഴിയും . ആരാണ് ആദ്യം ജോലി പൂർത്തിയാക്കുക ?
32 ആളുകൾക്ക് ഒരു ജോലി പൂർത്തിയാക്കുവാൻ 15 ദിവസം വേണമെങ്കിൽ 10 ദിവസം കൊണ്ട് ആ ജോലി പൂർത്തീകരിക്കുവാൻ എത്ര ആളുകൾ വേണം ?
The number of days to finish a work by A is double the number of days to finish the work by B. The number of days to finish the work by C is half the number of days to finish the work by B. A can finish the work in 12 days. If B works on the 1st day, A works on the 2nd day and C works on the 3rd day, again B works on the 4th day and so on, then the work is finished in ______ days.
12 ആളുകൾ ചേർന്ന് ഒരു ജോലി 15 ദിവസംകൊണ്ട് തീർക്കും. എന്നാൽ അതേ ജോലി 10 ആളുകൾ എത്ര ദിവസം കൊണ്ട് തീർക്കും?