App Logo

No.1 PSC Learning App

1M+ Downloads
A, B, and C can do a work separately in 18, 36 and 54 days, respectively. They started the work together, but B and C left 5 days and 10 days, respectively, before the completion of the work. In how many days was the work finished?

A12

B13

C15

D14

Answer:

B. 13

Read Explanation:

Solution: GIVEN: A, B, and C can do work separately in 18, 36, and 54 days and they started the work together, but B and C left 5 days and 10 days, respectively, before the completion of the work CONCEPT USED: L.C.M of number of days = Total work FORMULA USED: Efficiency = Total work/Number of days CALCULATION: A, B, and C can do work separately in 18, 36, and 54 days ⇒ Total work = L.C.M (18, 36, and 54) = 108 ⇒ Efficiency = Total work/Number of days ⇒ Efficiency of A = 108/18 = 6 ⇒ The efficiency of B = 108/36 = 3 ⇒ The efficiency of C = 108/54 = 2 Suppose, B and C doesn't leave till the work get completed ⇒ Work of B and C for 5 days and 10 days = (5 × 3 + 2 × 10) ⇒ 35 ⇒ Now Total work = 108 + 35 = 143 ⇒ Number of days required to complete the whole work when they start working together = Total work/Efficiency(A + B +C) ⇒ 143/(6 + 3 + 2) ⇒ 143/11 ⇒ 13 ∴ The required number of days to complete the whole work when they start working together is 13 days


Related Questions:

A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?
Working alone, A can do a job in 15 days and B can do the same job in 18 days. In how many days will the job be completed if both work together?
A ,B, C എന്നീ മൂന്നുപേർ ചേർന്ന് ഒരു ജോലി 12 ദിവസംകൊണ് ചെയ്യും. A, B എന്നിവർ മാത്രം അത് 16 ദിവസങ്ങൾ കൊണ്ട് ചെയ്യും. എങ്കിൽ C ഒറ്റയ്ക്ക് അത് എത്ര ദിവസം കൊണ്ട് ചെയ്യും?
2 men and 5 women can do a work in 12 days. 5 men 2 women can do that work in 9 days. Only 3 women can finish the same work in-
A can do a piece of work in 30 days, while B alone can do it in 40 days. In how many days can A and B working together do it?