Challenger App

No.1 PSC Learning App

1M+ Downloads
A, B, and C can do a work separately in 18, 36 and 54 days, respectively. They started the work together, but B and C left 5 days and 10 days, respectively, before the completion of the work. In how many days was the work finished?

A12

B13

C15

D14

Answer:

B. 13

Read Explanation:

Solution: GIVEN: A, B, and C can do work separately in 18, 36, and 54 days and they started the work together, but B and C left 5 days and 10 days, respectively, before the completion of the work CONCEPT USED: L.C.M of number of days = Total work FORMULA USED: Efficiency = Total work/Number of days CALCULATION: A, B, and C can do work separately in 18, 36, and 54 days ⇒ Total work = L.C.M (18, 36, and 54) = 108 ⇒ Efficiency = Total work/Number of days ⇒ Efficiency of A = 108/18 = 6 ⇒ The efficiency of B = 108/36 = 3 ⇒ The efficiency of C = 108/54 = 2 Suppose, B and C doesn't leave till the work get completed ⇒ Work of B and C for 5 days and 10 days = (5 × 3 + 2 × 10) ⇒ 35 ⇒ Now Total work = 108 + 35 = 143 ⇒ Number of days required to complete the whole work when they start working together = Total work/Efficiency(A + B +C) ⇒ 143/(6 + 3 + 2) ⇒ 143/11 ⇒ 13 ∴ The required number of days to complete the whole work when they start working together is 13 days


Related Questions:

15 ആളുകൾ 20 ദിവസം കൊണ്ട് ചെയ്തുതീർക്കുന്ന ജോലി 10 ആളുകൾക്ക് ചെയ്തുതീർക്കാൻ എത്ര ദിവസം വേണം?
A pipe can fill a cistern in 20 minutes whereas the cistern when full can be emptied by a leak in 28 minutes. When both are opened, The time taken to fill the cistern is:
12 പേർ 24 ദിവസം കൊണ്ട് തീർക്കുന്ന ഒരു ജോലി 16 പേർ എത്ര ദിവസം കൊണ്ട് തീർക്കും?
12 men and 16 women can complete a job in 5 days. 13 men and 24 women can complete the same job in 4 days. How long in days, will 5 men and 10 women take to complete the same job?
If 3 men or 4 women can plough a field in 43 days, how long will 7 men and 5 women take to plough it ?