App Logo

No.1 PSC Learning App

1M+ Downloads
A, B, and C can do a work separately in 18, 36 and 54 days, respectively. They started the work together, but B and C left 5 days and 10 days, respectively, before the completion of the work. In how many days was the work finished?

A12

B13

C15

D14

Answer:

B. 13

Read Explanation:

Solution: GIVEN: A, B, and C can do work separately in 18, 36, and 54 days and they started the work together, but B and C left 5 days and 10 days, respectively, before the completion of the work CONCEPT USED: L.C.M of number of days = Total work FORMULA USED: Efficiency = Total work/Number of days CALCULATION: A, B, and C can do work separately in 18, 36, and 54 days ⇒ Total work = L.C.M (18, 36, and 54) = 108 ⇒ Efficiency = Total work/Number of days ⇒ Efficiency of A = 108/18 = 6 ⇒ The efficiency of B = 108/36 = 3 ⇒ The efficiency of C = 108/54 = 2 Suppose, B and C doesn't leave till the work get completed ⇒ Work of B and C for 5 days and 10 days = (5 × 3 + 2 × 10) ⇒ 35 ⇒ Now Total work = 108 + 35 = 143 ⇒ Number of days required to complete the whole work when they start working together = Total work/Efficiency(A + B +C) ⇒ 143/(6 + 3 + 2) ⇒ 143/11 ⇒ 13 ∴ The required number of days to complete the whole work when they start working together is 13 days


Related Questions:

Pipes A and B can empty a full tank in 5 hours and 12 hours respectively. Pipe C can fill the same empty tank in 2 hours. If all the three pipes are opened together, then the tank will be filled in:
X ജോലിക്കാർക്ക് ഒരു ജോലി ചെയ്ത് തീർക്കാൻ 16 ദിവസം വേണം. എങ്കിൽ 2X ജോലിക്കാർക്ക് അതിന്റെ പകുതി ജോലി ചെയ്തു തീർക്കാൻ ആവശ്യമായ ദിവസം കണക്കാക്കുക.
20 buckets of water fill a tank when the capacity of each bucket is 13.5 litres. How many buckets will be required to fill the same tank ifthe capacity of each bucket is 9 litres?
'A' can do a piece of work in 10 days. He works at it for 8 days and then B finished the work in 16 days. How long will they take to complete the work if they do it together?
A and B can do a piece of work in 28 days and 35 days, respectively. They work on alternate days starting with A till the work gets completed. How long (in days) would it take A and B to complete the work?