A can do a piece of work in 10 days. He works at it for 4 days and then B finished the remaining work in 9 days. How long will they take to complete the work if they do it together?

A5 days

B6 days

C4 days

D16 days

Answer:

B. 6 days

Read Explanation:

  1. A's work: In 4 days, A completes 410=25\frac{4}{10} = \frac{2}{5} of the total work.

  2. Remaining work: 1−25=351 - \frac{2}{5} = \frac{3}{5} of the work is left.

  3. B's total capacity: B completes this 35\frac{3}{5} work in 9 days, meaning B can do the whole job alone in 9×53=15 days9 \times \frac{5}{3} = \mathbf{15\text{ days}}.

  4. Working together: Combined 1-day work = 110+115=3+230=530=16\frac{1}{10} + \frac{1}{15} = \frac{3+2}{30} = \frac{5}{30} = \frac{1}{6}.

  5. Final Answer: 6 days


Related Questions:

A യും B യും C യും കൂടി ഒരു ജോലി 4 ദിവസം കൊണ്ടു ചെയ്തുതീർക്കുന്നു. A തനിയെ 12 ദിവസം കൊണ്ടും B തനിയെ 18 ദിവസം കൊണ്ടും ചെയ്തുതീർത്താൽ C യ്ക്ക് തനിയെ ആ ജോലി ചെയ്യാൻ വേണ്ടി വരുന്ന ദിവസമെത്ര?
8 പുരുഷന്മാർക്കോ 12 കുട്ടികൾക്കോ ഒരു ജോലി ചെയ്യുന്നതിന് 25 ദിവസം വേണം. 6 പുരുഷന്മാർക്കും 11 കുട്ടികൾക്കും കൂടി ആ ജോലി ചെയ്യുന്നതിന് എത്ര ദിവസം വേണം?
മൂന്നു സംഖ്യകളുടെ അനുപാതം 3:5 :7 ആണ്.ആദ്യത്തെ സംഖ്യയും മൂന്നാമത്തെ സംഖ്യയും കൂട്ടിയാൽ രണ്ടാമത്തെ സംഖ്യയേക്കാൾ 40 കൂടുതലാണെങ്കിൽ ,ഏറ്റവും വലിയ സംഖ്യ എത്ര ?
ഒരു തീവണ്ടി ഒരു ടെലഗ്രാഫ് പോസ്റ്റ് 8 സെക്കൻഡ് കൊണ്ടും 105 മീറ്റർ നീളമുള്ള പാലം 20 സെകണ്ട് കൊണ്ടും കടന്നുപോകുന്നു. തീവണ്ടിയുടെ നീളം എത്ര ?
A machine fills 0.375 liters of water every second. How much does it fill in 8 seconds?