'A' can do a piece of work in 10 days. He works at it for 8 days and then B finished the work in 16 days. How long will they take to complete the work if they do it together?

A15 days

B13 y days

C14 days

D16 days

Answer:

B. 13 y days


Related Questions:

A can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will B alone complete 20% of the remaining work?
Two pipes are connected to a water tank. The first pipe can fill the tank in 10 minutes and the second pipe can empty it in 15 minutes. If both pipes opened simultaneously, then find the time in which the tank will be completely filled with water.
A and B can do a work in 12 days, B and C can do the same work in 15 days, and C and A can do the same work in 20 days. A, B and C will complete the work together in:
A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?
A can make a divider in 20 days, while B can make it in 50 days. If they work together and get Rs.3500, then find the share of B in the amount.