A can finish painting a sari in 11 days, B in 20 days and C in 55 days, if they work independently. In how many days can the work be completed if A is assisted by B on every odd numbered day and by C on every even numbered day till the work completes?

A9 days

B18 days

C12 days

D8 days

Answer:

D. 8 days

Read Explanation:

A's work rate = 1/11 (sari per day) B's work rate = 1/20 (sari per day) C's work rate = 1/55 (sari per day) Combined work rate of A and B = (1/11) + (1/20) = (20 + 11) / 220 = 31/220 (sari per day) Combined work rate of A and C = (1/11) + (1/55) = (5 + 1) / 55 = 6/55 (sari per day) Work done in 2 days = (31/220) + (6/55) = (31/220) + (24/220) = 55/220 = 1/4 (sari) Since 1/4 of the work is done in 2 days, it will take approximately 4 cycles to complete the work. So, 4 cycles * 2 days/cycle = 8 days. Work done in 8 days = 4 cycles * (1/4 sari/cycle) = 1 sari. The work can be completed in 8 days.


Related Questions:

A and B can complete a work in 10 days and 15 days, respectively. They got a total of Rs. 1,250 for that work. What will be B’s share?
Kartik can do a piece of work in 4 hours. Ishan can do it in 20 hours. With the assistance of Krish, they completed the work in 2 hours. In how many hours can Krish alone do it?

A can do 331333\frac{1}{3}% of a work in 10 days and B can do 662366\frac{2}{3}% of the same work in 8 days. Both together worked for 8 days then C alone completes the remaining work in 3 days. A and C together will complete 56\frac{5}{6} part of the original work in:

Kiran can do a certain piece of work in 15 days. Kiran and Garima can together do the same work in 10 days, and Kiran, Garima and Mehak can do the same work together in 9 days. In how many days can Kiran and Mehak do the same work?
ഒരു ക്ളോക്കിൽ 12 അടിക്കാൻ 22 സെക്കന്റ് സമയമെടുക്കും.6 അടിക്കാൻ എത്ര സെക്കന്റ് സമയം വേണം ?