App Logo

No.1 PSC Learning App

1M+ Downloads
A can do a piece of work in 16 days and the same work can be done by B in 24 days, If they work individually on alternate days (i.e., on the first day A does the work and on the second day A was on leave and B done the second-day work and so on.) and A starts the work, then find the total days required to complete the work.

A19 days

B18 days

C20 days

D10 days

Answer:

A. 19 days

Read Explanation:

Solution: Given: Time is taken by A to complete the work = 16 days Time is taken by B to complete the work = 24 days Formula used: Time is taken by A to complete the work = a days Time is taken by B to complete the work = b days Total unit of work = L.C.M of (a and b) units Calculation: Total unit of work = L.C.M of (16 and 24) = 48 units Efficiency of A = 4816 = 3 units a day Efficiency of B = 4824 = 2 units a day According to the question, Amount of work done by A on the first day = 3 units a day Amount of work done by B on the second day = 2 units a day In 2 days, the amount of work done = 5 units On multiplying 9 on both sides, In (2 × 9) days, the amount of work done = 5 × 9 units In 18 days, the amount of work done = 45 units Remaining amount of work = 48 - 45 = 3 units Amount of work done by A on the first day = 3 units a day Since the amount of work done by A on one day = 3 units a day Therefore, A will complete the 19th-day work. Therefore, The total time required to complete the work = 19 days Therefore, '19 days' is the required answer.


Related Questions:

A can count 100 eggs in 4 minutes while B can count the same number of eggs in 5 minutes. How much time will be required if they work together to count 450 eggs?
Kiran can do a certain piece of work in 15 days. Kiran and Garima can together do the same work in 10 days, and Kiran, Garima and Mehak can do the same work together in 9 days. In how many days can Kiran and Mehak do the same work?
The efficiency of A and B to do a work is in the ratio 3 ∶ 5. Working together they can complete a work in 30 days. In how many days A alone will complete that work?
എ, ബി എന്നിവർ ചേർന്ന് ഒരു പണി 12 ദിവസം കൊണ്ടു വര്സിക്കുന്നു. ബി, സി 15 ദിവസവും, എ, സി 20 ദിവസവും കൊണ്ട്. എ, ബി, സി മൂന്ന് പേരും ചേർന്ന് പണി നടത്തി തികയ്ക്കാൻ എത്ര ദിവസം?
Two pipes A and B can fill a tank in 15 and 30 minutes respectively. If both the pipes are used together, then how long will it take to fill the tank ?