Challenger App

No.1 PSC Learning App

1M+ Downloads
A can do a piece of work in 16 days and the same work can be done by B in 24 days, If they work individually on alternate days (i.e., on the first day A does the work and on the second day A was on leave and B done the second-day work and so on.) and A starts the work, then find the total days required to complete the work.

A19 days

B18 days

C20 days

D10 days

Answer:

A. 19 days

Read Explanation:

Solution: Given: Time is taken by A to complete the work = 16 days Time is taken by B to complete the work = 24 days Formula used: Time is taken by A to complete the work = a days Time is taken by B to complete the work = b days Total unit of work = L.C.M of (a and b) units Calculation: Total unit of work = L.C.M of (16 and 24) = 48 units Efficiency of A = 4816 = 3 units a day Efficiency of B = 4824 = 2 units a day According to the question, Amount of work done by A on the first day = 3 units a day Amount of work done by B on the second day = 2 units a day In 2 days, the amount of work done = 5 units On multiplying 9 on both sides, In (2 × 9) days, the amount of work done = 5 × 9 units In 18 days, the amount of work done = 45 units Remaining amount of work = 48 - 45 = 3 units Amount of work done by A on the first day = 3 units a day Since the amount of work done by A on one day = 3 units a day Therefore, A will complete the 19th-day work. Therefore, The total time required to complete the work = 19 days Therefore, '19 days' is the required answer.


Related Questions:

Kiran can do a certain piece of work in 15 days. Kiran and Garima can together do the same work in 10 days, and Kiran, Garima and Mehak can do the same work together in 9 days. In how many days can Kiran and Mehak do the same work?
There are 3 taps, A, B and C, in a tank. These can fill the tank in 10 h, 20 h and 25 h, respectively. At first, all three taps are opened simultaneously. After 2 h, tap C is closed and tap A and B keep running. After 4 h, tap B is also closed. The remaining tank is filled by tap A alone. Find the percentage of work done by tap A itself.
A and B together can complete a work in 30 day. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
Two pipes A and B can fill a tank in 15 hours and 20 hours, respectively, while a third pipe C can empty the full tank in 30 hours. If all the three pipes operate simultaneously, in how much time will the tank, initially empty, be filled?
A certain number of persons can finish a task in 85 days. If there were 15 persons more, it would have taken 25 days less for the task to be completed. How many persons are there in the beginning?