A can finish a work in 20 days. A and B can together finish a work in 12 days.Then B alone can finish the work in

A24 days

B28 days

C25 days

D30 days

Answer:

D. 30 days

Read Explanation:

Total work = lcm[ 20, 12] = 60 A's efficiency = 60/20 = 3 A + B's efficiency = 60/12 = 5 B's efficiency = 5 - 3 = 2 Time taken by B alone to complete the work = Total work / B's efficiency = 60/2 = 30 days


Related Questions:

ഒരാൾ 12 ദിവസം കൊണ്ട് ചെയ്ത് തീർക്കുന്ന ജോലി നാല് ആളുകൾ എത്ര ദിവസം കൊണ്ട് ചെയ്തുതീർക്കും?
The number of days to finish a work by A is double the number of days to finish the work by B. The number of days to finish the work by C is half the number of days to finish the work by B. A can finish the work in 12 days. If B works on the 1st day, A works on the 2nd day and C works on the 3rd day, again B works on the 4th day and so on, then the work is finished in ______ days.
A ഒരു ജോലി 20 ദിവസം എടുത്തു പൂർത്തിയാക്കുന്നു A യും B യും കൂടി ഒരുമിച്ച് ജോലി പൂർത്തീകരിക്കാൻ 12 ദിവസം എടുക്കും എന്നാൽ B മാത്രമായി പ്രസ്തുത ജോലി പൂർത്തീകരിക്കാൻ എത്ര ദിവസം എടുക്കും ?
Two pipes can fill a tank in 30 hours and 40 hours, respectively. Find the time (in hours) taken to fill the tank when both the pipes are opened simultaneously.
6 ആളുകൾ ഒരു ജോലി 10 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്നു . എന്നാൽ ഒരാൾ ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?