A can finish a work in 20 days. A and B can together finish a work in 12 days.Then B alone can finish the work in

A24 days

B28 days

C25 days

D30 days

Answer:

D. 30 days

Read Explanation:

a -> 20 -> 3 a + b -> 12 - > 5 lcm(12 and 20 ) = 60 60/2 = 30 days


Related Questions:

Pipes A, B and C can fill a tank in 15, 30 and 40 hours, respectively. Pipes A, B and C are opened at 6 a.m., 8 a.m. and 10 a.m., respectively, on the same day. When will the tank be full?
A and B can do a job in 10 days and 5 days, respectively. They worked together for two days, after which B was replaced by C and the work was finished in the next three days. How long will C alone take to finish 60% of the job?
A and B can do a work together in 18 days. A is three times as efficient as B. In how many days can B alone complete the work?
A and B working separately can finish a work in 15 days and 20 days. respectively. If they work on alternate days. A starting first, and if the work goes on for 8 days, what part of the work will be left unfinished?
A can finish 3/5th of a task in 6 days and B can finish 2/3th of the same task in 12 days. A and B worked together for 5 days. C alone completed the remaining task in 8 days. B and C, working together, will complete the same task in: