P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?

A48 days

B42 days

C45 days

D51 days

Answer:

C. 45 days

Read Explanation:

Solution:

GIVEN:

P and Q together can complete a work in 20 days

P alone can complete same work in 36 days.

CONCEPT:

We will use L.C.M. approach

CALCULATION:

image.png

Let work be L.C.M. of 20 and 36 i.e. 180 units

P and Q together work in one day = 180/20 = 9 units

P work in one day = 180/36 = 5 units

→ Q work in one day = (9 – 5) = 4 units

→ So, time taken by Q to complete work = 180/4 = 45 days.


Related Questions:

Working together, P, Q and R reap a field in 6 days. If P can do it alone in 10 days and Q in 24 days, in how many days will R alone be able to reap the field?
1f in the year 2010 January 17 is a Sunday, then what is the day of March 26?
Ravi, Manish and Naveen alone can complete a work in 30 days, 15 days and 10 days respectively. They start the work together but Ravi leaves the work after 2 days of the starting of the work and Manish leaves the work after 3 days more. In how many days Naveen will complete the remaining work?
A യും B യും ഒരുമിച്ച് 40 ദിവസത്തിനുള്ളിൽ ഒരു ജോലി ചെയ്യുന്നു. B യും C യും ഒരുമിച്ച് 25 ദിവസത്തിനുള്ളിൽ ചെയ്യുന്നു. എയും ബിയും ഒരുമിച്ച് ജോലി ചെയ്യാൻ തുടങ്ങി, എ 6 ദിവസത്തിന് ശേഷം ജോലി ഉപേക്ഷിച്ചു, ബി 8 ദിവസത്തിന് ശേഷം ജോലി ഉപേക്ഷിച്ചു. A പോയതിനു ശേഷം, C ജോലിയിൽ ചേരുകയും C 40.5 ദിവസത്തിനുള്ളിൽ ജോലി പൂർത്തിയാക്കുകയും ചെയ്തു, C-യ്ക്ക് മാത്രം എത്ര ദിവസത്തിനുള്ളിൽ ജോലി പൂർത്തിയാക്കാൻ കഴിയും?
A, B and C can do a piece of work in 12 days, 14 days and 16 days respectively. All three of them started the work together and after working for four days C leaves the job, B left the job 4 days before completion of the work. Find the approximate time required to complete the work. (in days)