A certain number of men complete a piece of work in 60 days. If there were 8 men more, the work could be finished in 10 days less. How many men were originally there?

A20 men

B30 men

C40 men

D50 men

Answer:

C. 40 men

Read Explanation:

60 * x=>50(x+8) => x = 50x8 / 60-50 = 400/10 = 40 men


Related Questions:

A, B and C contract to do a work for Rs. 4200. A can do the work in 6 days, B in 10 days and C in 12 days. If they work together to do the work, what is the share of C (in Rs.)?
A സ്കൂൾ പദ്ധതി 20 ദിവസം കൊണ്ട് പൂർത്തിയാക്കി. A-യെക്കാൾ 25% കൂടുതൽ കാര്യക്ഷമതയുണ്ടെങ്കിൽ B ഇതേ ജോലി പൂർത്തിയാക്കാൻ എത്ര ദിവസമെടുക്കും?
Abhay and Bharat can complete a certain piece of work in 17 and 10 days, respectively, They started to work together, and after 3 days, Bharat left. In how many days will Abhay complete the remaining work?
A work could be completed in 22 days. However due to three workers being absent, it was completed in 24 days. The original number of workers was.
4 പുരുഷന്മാർക്കും 5 സ്ത്രീകൾക്കും 15 ദിവസത്തിനുള്ളിൽ ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും, അതേസമയം 9 പുരുഷന്മാർക്കും 6 സ്ത്രീകൾക്കും 10 ദിവസം കൊണ്ട് അത് പൂർത്തിയാക്കാൻ കഴിയും. ഇതേ ജോലി 7 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ, 4 പുരുഷന്മാരെ എത്ര സ്ത്രീകൾ സഹായിക്കണം?