Challenger App

No.1 PSC Learning App

1M+ Downloads
A can do a piece of work in 30 days, while B alone can do it in 40 days. In how many days can A and B working together do it?

A17 and 1/7

B27 and 1/7

C42 and 3/4

D70

Answer:

A. 17 and 1/7

Read Explanation:

The LCM of (30 , 40) = 120 Total work = 1120 unit Efficiency of A = 120/30 = 4 Efficiency of B = 120/40 = 3 Efficiency of A + B = 4 + 3 = 7 Time taken by A and B to complete the work = 120/7 = 17 1/7 days


Related Questions:

A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for the first half of the day daily, then in how many days will A and B together complete the work?
A pipe can fill a tank in 9 hours. Another pipe can empty the filled tank in 27 hours. If both the pipes are opened simultaneously, then the time (in hours) in which the tank will be two-third filled, is:
ഒരു ടാങ്കിലേക്ക് 2 പൈപ്പുകൾ തുറന്നു വച്ചിരിക്കുന്നു. 6 മിനുറ്റുകൊണ്ട് ടാങ്ക് നിറയും. ഒന്നാമത്തെ പൈപ്പ് മാത്രം തുറന്നു വച്ചാൽ 10 മിനിറ്റുകൊണ്ട് നിറയും. എങ്കിൽ രണ്ടാമത്തെ ടാപ്പ് മാത്രംതുറന്നു വച്ചാൽ എത്ര മിനുറ്റുകൊണ്ട് നിറയും ?
X ജോലിക്കാർക്ക് ഒരു ജോലി ചെയ്ത് തീർക്കാൻ 16 ദിവസം വേണം. എങ്കിൽ 2X ജോലിക്കാർക്ക് അതിന്റെ പകുതി ജോലി ചെയ്തു തീർക്കാൻ ആവശ്യമായ ദിവസം കണക്കാക്കുക.
ഒരു ജോലി 8 പുരുഷന്മാരോ 12 സ്ത്രീകളോ 25 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ കഴിയുമെങ്കിൽ ,10 പുരുഷന്മാരും 5 സ്ത്രീകളും എത്ര ദിവസത്തിനുള്ളിൽ അതേ ജോലി പൂർത്തിയാക്കും ?