A certain number of persons can finish a task in 85 days. If there were 15 persons more, it would have taken 25 days less for the task to be completed. How many persons are there in the beginning?

A30

B45

C40

D36

Answer:

D. 36

Read Explanation:

Solution:

Given:

Time taken to finish task = 85 days

No. of extra men added = 15

Time taken to finish the work with 15 extra men = Initial time - 25 days

= 85 - 25

= 60 days

Formula used:

M1 × D1 = M2 × D2

Calculation:

Let the initial number of men working = N

∴ N × 85 = (N + 15) × 60

⇒ 85N = 60N + 900

⇒ 25N = 900

⇒ N = 900/25

⇒ N = 36

∴ 36 men were working initially.


Related Questions:

A can do a piece of work in 16 days and the same work can be done by B in 24 days, If they work individually on alternate days (i.e., on the first day A does the work and on the second day A was on leave and B done the second-day work and so on.) and A starts the work, then find the total days required to complete the work.
ഒരു ക്ലോക്കിൽ സമയം 8:20 pm കാണിക്കുന്നു എങ്കിൽ മിനിറ്റു സൂചിയും മണിക്കൂർ സൂചിയും തമ്മിലുള്ള കോണളവ് എത്ര ?
A യും B യും ചേർന്ന് 12 ദിവസം കൊണ്ടും, A യും C യും ചേർന്ന് 8 ദിവസം കൊണ്ടും, B യും C യും ചേർന്ന് 6 ദിവസം കൊണ്ടും ഒരു ജോലി പൂർത്തിയാക്കാമെങ്കിൽ, B ഒറ്റയ്ക്ക് ആ ജോലി എത്ര ദിവസം കൊണ്ട് പൂർത്തിയാക്കും ?
If 4 men can reap a field in 5 days working 9 hours a day, in how many hours can 10 men reap the same field working 3 days?
A and B can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete 4/9 part of the original work in: