Amit can complete a piece of work in 120 days. Amit and Sejal can complete the same work in 72 days. They started together but Sejal left after working for 20 days. Find the approximate number of days in which Amit will complete the remaining work.

A87 days

B76 days

C90 days

D84 days

Answer:

A. 87 days

Read Explanation:

Solution:

Given:

Amit's work time = 120 days; Amit+Sejal's work time = 72 days; Sejal worked for 20 days

Solution:

 

Time taken

Total work

Efficiency

Amit

120 

360

3

Amit + Sejal

72

5

 

Total work = 360

Since, they work together for 20 days,

So, 

Work done in 20 days by both = 5 × 20 = 100

Now, 

Remaining work = 360 - 100 = 260

So, Time taken by Amit to complete the remaining work

⇒ 260/3 = 86.66 ≈ 87 days

∴ The correct answer is option (A).


Related Questions:

12 പുരുഷന്മാരോ,18 സ്ത്രീകളോ ഒരു ജോലി 14 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്നു. എന്നാൽ 8 പുരുഷന്മാരും 16 സ്ത്രീകളും ചേർന്ന് അതേ ജോലി എത്ര സമയത്തിനുള്ളിൽ ചെയ്തു തീർക്കും ?
After 60 litres of petrol was poured into an empty storage tank, it was still 10% empty. How much petrol (in litres, rounded off to two decimal place) must be poured into the storage tank in order to fill it?
P, Q and R together do a piece of work for 535. P working alone can do it in 5 days. Q alone can do it in 6 days and R alone can do it in 7 days. Then what will be the share of R for its work.
Two pipes can fill a tank in 15 hours and 4 hours, respectively, while a third pipe can empty it in 12 hours. How long (in hours) will it take to fill the empty tank if all the three pipes are opened simultaneously?
20 ആളുകൾ 20 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ജോലി ചെയ്യാൻ 5 പേർക്ക് എത്ര ദിവസം വേണം ?