51 men can complete a work in 12 days. Four days after they started working 6 more men joined them. How many days will they now take to complete the remaining work?

A$$8\frac{1}{19}$ days$

B$$5\frac{9}{19}$ days$

C$$7\frac{3}{19}$ days$

D$$6\frac{7}{19}$ days$

Answer:

$$7\frac{3}{19}$ days$

Read Explanation:

73197\frac{3}{19} days

Related Questions:

60 ആളുകൾ 15 ദിവസം കൊണ്ട് തീർക്കുന്ന ജോലി 12 ദിവസം കൊണ്ട് തീർക്കണമെങ്കിൽ എത്ര പേരെ കൂടുതൽ നിയമിക്കണം ?
Anjali can do a certain piece of work in 16 days. Anjali and Ayushi can together do the same work in 10 days, and Anjali, Ayushi and Ankita can do the same work together in 8 days. In how many days can Anjali and Ankita do the same work?
Vijay can do a piece of work in 4 hours. Ajay can do it in 28 hours. With the assistance of Amit, they completed the work in 3 hours. In how many hours can Amit alone do it?
A, B, C can together complete the work in 12 days. If A is thrice faster than B, and B is twice faster than C, B alone can do the work in:
A ഒരു ജോലി 60 ദിവസത്തിലും B 20 ദിവസത്തിലും ചെയ്യുന്നു. രണ്ടുപേരും ചേർന്ന് എത്ര ദിവസത്തിനുള്ളിൽ ജോലി പൂർത്തിയാക്കും?