C is four times more efficient as a worker than D, which allows C to complete a work in 45 days less than D. If they work together, they can finish the work in:

A10 days

B12 days

C15 days

D18 days

Answer:

B. 12 days

Read Explanation:

Let D's efficiency be 1 unit/day.

Then C's efficiency is 4 units/day.

So, if D takes (x) days to finish the work, C takes (\frac{x}{4}) days.

Given:

xx4=45x-\frac{x}{4}=45

3x4=45\frac{3x}{4}=45

x=60

So:

  • D takes 60 days

  • C takes 15 days

Their combined work rate is:

115+160\frac{1}{15}+\frac{1}{60}
=4+160=\frac{4+1}{60}


=560=\frac{5}{60}


=112=\frac{1}{12}

Hence, together they will complete the work in:

12 days\boxed{12\text{ days}}


Related Questions:

A and B start a business. A invests 2 times more than B. After 8 months, A withdraws half of his capital, and B triples his capital. If the total profit after one year is ₹75,000, find the share of A.
Two pipes A and B can fill a tank in 24 minutes and 32 minutes respectively. If both the pipes are opened simultaneously, after how much time should A be closed so that the tank is full in 20 minutes?
The area of a sector of a circle with radius 7 cm and central angle 90° is :
20 ആളുകൾ 6 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി 8 ആളുകൾ എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും
6 ആളുകൾ ഒരു ജോലി 10 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്നു . എന്നാൽ ഒരാൾ ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?