C is four times more efficient as a worker than D, which allows C to complete a work in 45 days less than D. If they work together, they can finish the work in:

A10 days

B12 days

C15 days

D18 days

Answer:

B. 12 days

Read Explanation:

Let D's efficiency be 1 unit/day.

Then C's efficiency is 4 units/day.

So, if D takes (x) days to finish the work, C takes (\frac{x}{4}) days.

Given:

x−x4=45x-\frac{x}{4}=45

3x4=45\frac{3x}{4}=45

x=60

So:

  • D takes 60 days

  • C takes 15 days

Their combined work rate is:

115+160\frac{1}{15}+\frac{1}{60}
=4+160=\frac{4+1}{60}


=560=\frac{5}{60}


=112=\frac{1}{12}

Hence, together they will complete the work in:

12 days\boxed{12\text{ days}}


Related Questions:

ഒരു ടാങ്ക് അതിന്റെ 3/4 ഭാഗം വെള്ളം നിറച്ചിരിയ്ക്കുന്നു. 5 ലിറ്റർ വെള്ളം കൂടി ഒഴിച്ചാൽ അതിന്റെ 4/5 ഭാഗം നിറയുമെങ്കിൽ ടാങ്കിന്റെ യഥാർത്ഥ ശേഷി എത്ര ?
Two pipes A and C can fill a tank in 10 hours and 15 hours respectively. If A is open all the time and C is open for 30 minutes, then find the time needed for the tank to be filled.
A and B together can complete a work in 12 days. B and C together can complete the same work in 15 days. C and A together can do it in 20 days. In how many days can A alone complete the job ?
A machine fills 0.375 liters of water every second. How much does it fill in 8 seconds?
A, B, C എന്നിവർക്ക് ഒരു ജോലി യഥാക്രമം 40, 60, 80 ദിവസങ്ങൾ കൊണ്ട് പൂർത്തിയാക്കാൻ കഴിയും. അവർ ഒരുമിച്ച് ജോലി ചെയ്യാൻ തുടങ്ങി. ജോലി പൂർത്തിയാകുന്നതിന് 11 ദിവസം മുമ്പ് A-യും 8 ദിവസം മുമ്പ് B-യും ജോലിയിൽ നിന്ന് മാറിനിന്നു എങ്കിൽ, അവർ എത്ര ദിവസത്തിനുള്ളിൽ ജോലി പൂർത്തിയാക്കും?