Dangling phenomenon in a network diagram

Ashould be increased to the maximum possible extent.

Bshould be avoided.

Cshould be encouraged.

Dshould be inserted compulsorily.

Answer:

B. should be avoided.

Read Explanation:

Dangling phenomenon in a network diagram should be avoided as it refers to an event not connected to another event by an activity. To avoid dangling, a dummy activity can be introduced, which is an imaginary activity used to show the dependency relationship or connectivity between two or more activities. It is represented by a datted arrow