App Logo

No.1 PSC Learning App

1M+ Downloads
Positive slack in PERT indicates

AAhead of schedule

BBeyond of schedule

CAs per schedule

DCritical Path

Answer:

A. Ahead of schedule

Read Explanation:

Positive slack indicates that the project is ahead of schedule and has excess resources. It is the difference between the latest allowable occurrence time and the earliest expected time. The equation for slack is Slack = TL - TE. When TL is greater than TE, the slack is positive. Zero slack means the project is on schedule, while negative slack indicates the project is behind schedule due to a lack of resources.


Related Questions:

Simplex problem is considered as infeasible when
When total supply is equal to the total demand for a transportation problem, it is termed as a/an _____________ transportation problem.
The artificial activity which indicates that an activity following it cannot be started unless the preceding activity is complete, is known as-
Dummy activities are used in a network to
As per one of the assumptions of linear programming problem in operation research, objective function and constraints are assumed to be _____________