Positive slack in PERT indicates

AAhead of schedule

BBeyond of schedule

CAs per schedule

DCritical Path

Answer:

A. Ahead of schedule

Read Explanation:

Positive slack indicates that the project is ahead of schedule and has excess resources. It is the difference between the latest allowable occurrence time and the earliest expected time. The equation for slack is Slack = TL - TE. When TL is greater than TE, the slack is positive. Zero slack means the project is on schedule, while negative slack indicates the project is behind schedule due to a lack of resources.


Related Questions:

Which of the following artificial activity suggests that an activity following it cannot happen unless, the previous activity is completed?
As per one of the assumptions of linear programming problem in operation research, objective function and constraints are assumed to be _____________
For the single server with Poisson arrival, with the decrease in the mean of exponential service times, the average waiting time is going to reduce
The cost of providing service in a queueing system increases with
The first and last activities of a network diagram