App Logo

No.1 PSC Learning App

1M+ Downloads
If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 men do the same work by working 6 hours a day?

A12

B15

C16

D10

Answer:

D. 10

Read Explanation:

Total work = M × H × D 10 × 12 × 7 = 14 × d × 6 D = (10 × 12 × 7)/(14 × 6) D = 10 days


Related Questions:

Prakash and Vinesh can complete a certain piece of work in 10 and 8 days, respectively, They started to work together, and after 3 days, Vinesh left. In how many days will Prakash complete the remaining work?
Thirty men can complete a work in 36 days. In how many days can 18 men complete the same piece of work?
A can do a piece of work in 16 days and the same work can be done by B in 24 days, If they work individually on alternate days (i.e., on the first day A does the work and on the second day A was on leave and B done the second-day work and so on.) and A starts the work, then find the total days required to complete the work.
A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?
A , B എന്നിവർക്ക് യഥാക്രമം 15 ദിവസവും 10 ദിവസവും ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. അവർ ഒരുമിച്ച് ജോലി ചെയ്യാൻ തുടങ്ങി, പക്ഷേ 2 ദിവസത്തിന് ശേഷം Bക്ക് പോകേണ്ടി വന്നു, A മാത്രം ബാക്കിയുള്ള ജോലി പൂർത്തിയാക്കി. A പണി പൂർത്തിയാക്കാൻ എത്ര ദിവസം എടുക്കും?