Challenger App

No.1 PSC Learning App

1M+ Downloads
If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 men do the same work by working 6 hours a day?

A12

B15

C16

D10

Answer:

D. 10

Read Explanation:

Total work = M × H × D 10 × 12 × 7 = 14 × d × 6 D = (10 × 12 × 7)/(14 × 6) D = 10 days


Related Questions:

Two pipes, A and B, can fill the tank in 60 hours and 90 hours, respectively. If both the pipes are opened simultaneously, in how many hours will 75% of the tank be filled?
Pipes A, B and C can fill a tank in 15, 30 and 40 hours, respectively. Pipes A, B and C are opened at 6 a.m., 8 a.m. and 10 a.m., respectively, on the same day. When will the tank be full?
A can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
A യ്ക്ക് 15 ദിവസം കൊണ്ടും B യ്ക്ക് 20 ദിവസം കൊണ്ടും ഒരു ജോലി ചെയ്യാൻ കഴിയും. അവർ 4 ദിവസത്തേക്ക് ഒരുമിച്ച് ജോലി ചെയ്യുകയാണെങ്കിൽ, ശേഷിക്കുന്ന ജോലിയുടെ അംശം?
ഒരു ക്ലോക്കിൽ സമയം 8:20 pm കാണിക്കുന്നു എങ്കിൽ മിനിറ്റു സൂചിയും മണിക്കൂർ സൂചിയും തമ്മിലുള്ള കോണളവ് എത്ര ?