Challenger App

No.1 PSC Learning App

1M+ Downloads
A can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will A alone complete 60% of the remaining work?

A15

B18

C10

D7

Answer:

D. 7

Read Explanation:

Solution: GIven: A completes the work in 35 days B completes the work in 15 days Concept used: A's one day work is 1/35 B's one day work is 1/15 Calculation: A + B = (1/35) + (1/15) ⇒ A + B = (7 + 3)/105 = 2/21 Work completed by A + B in 7 days ⇒ (2/21) × 7 = 2/3 Remaining work = 1 - (2/3) = 1/3 1/3 work is left A will complete it in = 35 × (1/3) = 35/3 Asked in question 60% of the remaining work ⇒ (35/3) × (60/100) =7 ∴ A will take 7 days. By LCM method Time Total work(LCM of time) Efficiency(total work/time) A 35 3 105 B 15 7 A + B = 3 + 7 =10 A + B workes for 7 days = 10 × 7 = 70 Reamning work = 105 - 70 = 35 60% of the remaining work = 35 × (60/100) = 21 A complete it = 21/3 = 7 ∴ A will take 7 days.


Related Questions:

Amit can complete a piece of work in 120 days. Amit and Sejal can complete the same work in 72 days. They started together but Sejal left after working for 20 days. Find the approximate number of days in which Amit will complete the remaining work.
F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?
A and B together complete a work in 8 days. If B is 25% more efficient than A, then in how many days will A alone complete the same work?
10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days will they take to complete it ?
A ക്ക് 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. A യും B യും ചേർന്ന് 8 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ കഴിയും. B മാത്രം ജോലി പൂർത്തിയാക്കാൻ എത്ര സമയമെടുക്കും?