App Logo

No.1 PSC Learning App

1M+ Downloads
A can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will A alone complete 60% of the remaining work?

A15

B18

C10

D7

Answer:

D. 7

Read Explanation:

Solution: GIven: A completes the work in 35 days B completes the work in 15 days Concept used: A's one day work is 1/35 B's one day work is 1/15 Calculation: A + B = (1/35) + (1/15) ⇒ A + B = (7 + 3)/105 = 2/21 Work completed by A + B in 7 days ⇒ (2/21) × 7 = 2/3 Remaining work = 1 - (2/3) = 1/3 1/3 work is left A will complete it in = 35 × (1/3) = 35/3 Asked in question 60% of the remaining work ⇒ (35/3) × (60/100) =7 ∴ A will take 7 days. By LCM method Time Total work(LCM of time) Efficiency(total work/time) A 35 3 105 B 15 7 A + B = 3 + 7 =10 A + B workes for 7 days = 10 × 7 = 70 Reamning work = 105 - 70 = 35 60% of the remaining work = 35 × (60/100) = 21 A complete it = 21/3 = 7 ∴ A will take 7 days.


Related Questions:

A fort is provisioned for 32 days for some soldiers. After 4 days, a reinforcement of 150 soldiers arrived and the food will now last for 21 days only. How many soldiers were there in the fort in the beginning?
Anu can type 40 pages of a book in 10 hours. Anu and Mohit together can type 270 pages in 54 hours. In what time (in hours) can Mohit alone type 20 pages?
10 ആളുകൾക്ക് ഒരു ജോലി ചെയ്യാൻ 8 ദിവസം വേണം. അതേ ജോലി ചെയ്യാൻ 20 ആളുകൾക്ക് എത്ര ദിവസം വേണം ?
A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work?
ഒരാൾ ഒരു ദിവസം കൊണ്ട് 2 മീറ്റർ × 2 മീറ്റർ × 2 മീറ്റർ സൈസിൽ ഒരു കുഴി നിർമ്മിക്കും. ഇതേ നിരക്കിൽ 3 പേർ ചേർന്ന് 4 മീറ്റർ × 4 മീറ്റർ × 4 മീറ്റർ സൈസിൽ ഒരു കുഴി നിർമ്മിക്കാൻ എത്ര ദിവസം വേണം?