App Logo

No.1 PSC Learning App

1M+ Downloads
If 16 men or 28 women can do a work in 40 days. How long 24 men and 14 women will take to complete the work ?

A15 days

B18 days

C20 days

D22 days

Answer:

C. 20 days

Read Explanation:

16 men = 28 women 8 men = 14 women 24 men + 14 women = 24 men + 8 men = 32 men 16 men can do a piece of work in 40 days 1 men can do the same work in (40 × 16) days Then 32 men can do the same work in (40 × 16)/32 = 20 days


Related Questions:

A ഒരു ജോലി 8 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്നു. അതേ ജോലി B, 10 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും. എന്നാൽ A യും B യും ചേർന്ന് ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാം?
Had been one man less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?
The efficiency of A and B to do a work is in the ratio 3 ∶ 5. Working together they can complete a work in 30 days. In how many days A alone will complete that work?
A യും B യും ചേർന്ന് 12 ദിവസം കൊണ്ടും, A യും C യും ചേർന്ന് 8 ദിവസം കൊണ്ടും, B യും C യും ചേർന്ന് 6 ദിവസം കൊണ്ടും ഒരു ജോലി പൂർത്തിയാക്കാമെങ്കിൽ, B ഒറ്റയ്ക്ക് ആ ജോലി എത്ര ദിവസം കൊണ്ട് പൂർത്തിയാക്കും ?
Pipes A and B can empty a full tank in 5 hours and 12 hours respectively. Pipe C can fill the same empty tank in 2 hours. If all the three pipes are opened together, then the tank will be filled in: