In PERT analysis, a critical activity has:

AMaximum float

BZero float

CMaximum cost

DMinimum cost

Answer:

B. Zero float

Read Explanation:

Critical activity in PERT analysis has zero float and lies on the critical path. Float is the relaxation or delay provided to any activity. Total Float (TF) is the maximum delay, Free Float (FF) is the relax or delay without affecting EST (Earliest start time) of successor activity and Independent Float (IF) is relax or delay without affecting EST of successor activity and LFT (Latest Finish Time) of predecessor activity.


Related Questions:

Monte Carlo simulation of queues is used when
The term 'jockeying' in queuing theory refers to
Little's law is the relationship between

Consider the following statements in respect of PERT and CPM: Which of the statements are correct?

  1. PERT is event-oriented while CPM is activity-oriented.
  2. PERT is probabilistic while CPM is deterministic.
  3. Levelling and smoothing are the techniques related to resource scheduling in CPM.
    Modified distribution method is used for