In PERT analysis, a critical activity has:

AMaximum float

BZero float

CMaximum cost

DMinimum cost

Answer:

B. Zero float

Read Explanation:

Critical activity in PERT analysis has zero float and lies on the critical path. Float is the relaxation or delay provided to any activity. Total Float (TF) is the maximum delay, Free Float (FF) is the relax or delay without affecting EST (Earliest start time) of successor activity and Independent Float (IF) is relax or delay without affecting EST of successor activity and LFT (Latest Finish Time) of predecessor activity.


Related Questions:

When total supply is equal to the total demand for a transportation problem, it is termed as a/an _____________ transportation problem.
Positive slack in PERT indicates
In a transportation problem North-West corner rule would yield :
In PERT analysis, the possible number of time estimates for activities linking up two events are -
______________ may be defined as any adjustment to the arrow diagram which becomes necessary owing to departure from the project schedule laid down earlier.