In PERT analysis, a critical activity has:

AMaximum float

BZero float

CMaximum cost

DMinimum cost

Answer:

B. Zero float

Read Explanation:

Critical activity in PERT analysis has zero float and lies on the critical path. Float is the relaxation or delay provided to any activity. Total Float (TF) is the maximum delay, Free Float (FF) is the relax or delay without affecting EST (Earliest start time) of successor activity and Independent Float (IF) is relax or delay without affecting EST of successor activity and LFT (Latest Finish Time) of predecessor activity.


Related Questions:

The artificial activity which indicates that an activity following it cannot be started unless the preceding activity is complete, is known as-
When total supply is equal to the total demand for a transportation problem, it is termed as a/an _____________ transportation problem.
The primary objective of crashing in CPM is
Positive slack in PERT indicates
For the single server with Poisson arrival, with the decrease in the mean of exponential service times, the average waiting time is going to reduce