Jewel and Angelina together can paint a hall in 6 days. Jewel alone can paint it in 8 days. In how many days can Angelina alone paint it?

A24

B14

C48

D16

Answer:

A. 24

Read Explanation:

The correct answer is Option A (24 days).

Step-by-Step Solution

  1. Find the daily work rates:

    • Together (Jewel + Angelina): They finish in 6 days, so in one day they do 1/61/6 of the work.

    • Jewel alone: She finishes in 8 days, so in one day she does 1/81/8 of the work.

  2. Calculate Angelina's daily work rate:
    To find Angelina's rate, subtract Jewel's rate from their combined rate:
    Angelina’s Rate=16−18\text{Angelina's Rate} = \frac{1}{6} - \frac{1}{8}

  3. Solve the fraction:
    Find a common denominator (which is 24):
    424−324=124\frac{4}{24} - \frac{3}{24} = \mathbf{\frac{1}{24}} This means Angelina finishes 1/241/24 of the hall every day.

  4. Find the total days:
    If she does 1/241/24 of the work per day, she will need 24 days to finish the whole hall.


Related Questions:

മൂന്നു സംഖ്യകളുടെ അനുപാതം 3:5 :7 ആണ്.ആദ്യത്തെ സംഖ്യയും മൂന്നാമത്തെ സംഖ്യയും കൂട്ടിയാൽ രണ്ടാമത്തെ സംഖ്യയേക്കാൾ 40 കൂടുതലാണെങ്കിൽ ,ഏറ്റവും വലിയ സംഖ്യ എത്ര ?
A cistern can be filled by a tap in 6 hours and emptied by an outlet pipe in 7.5 hours. How long will it take to fill the cistern if both the tap and the pipe are opened together?
The area of a sector of a circle with radius 7 cm and central angle 90° is :
A machine fills 0.375 liters of water every second. How much does it fill in 8 seconds?
R ഒരു ജോലി പൂർത്തിയാക്കാൻ എടുക്കുന്ന സമയം, M-ന്റെ സമയത്തിന്റെ 2 മടങ്ങും S-ന്റെ സമയത്തിന്റെ 3 മടങ്ങുമാണ്. R, M, S എന്നിവർ ഒരുമിച്ച് പ്രവർത്തിച്ചാൽ ആ ജോലി 4 ദിവസത്തിൽ പൂർത്തിയാക്കും. ഓരോരുത്തരും ഒറ്റയ്ക്ക് ജോലി പൂർത്തിയാക്കാൻ എടുക്കുന്ന സമയം?