Jitesh and Kamal can complete a certain piece of work in 7 and 11 days, respectively, They started to work together, and after 3 days, Kamal left. In how many days will Jitesh complete the remaining work?

A161/79

B161/77

C164/78

D162/77

Answer:

B. 161/77

Read Explanation:

161/77


Related Questions:

Two taps can fill together a tank in 6 hr 40 minutes. One can fill it independently in 12 hrs, the other can fill in
Two pipes A and B can fill a tank in 6 hours and 8 hours respectivley. If both the pipes are opened together, then after how many hours should B be closed so that the tank is full in 4 hours ?
Raju can complete a work in 20 days, which Bobby, Arjun and Habib can finish Independently in 27, 30 and 36 days respectively, Raju and Arjan starts doing this work jointly and continues on it for 4 days and stops working. If one of Habib and Hobby has to complete the work, how many more days they may take respectively?
Three pipes can fill a tank in 12 min, 15min, 20 min respectively. If all the three pipes are opened sumultaneously then the tank will be filled in
A and B together can finish a work in 16 days, while B can do the same work alone in 24 days. In how many days can A alone finish the work ?