App Logo

No.1 PSC Learning App

1M+ Downloads
Jitesh and Kamal can complete a certain piece of work in 7 and 11 days, respectively, They started to work together, and after 3 days, Kamal left. In how many days will Jitesh complete the remaining work?

A161/79

B161/77

C164/78

D162/77

Answer:

B. 161/77

Read Explanation:

161/77


Related Questions:

7 ആളുകൾക്ക് ഒരു ജോലി പൂർത്തിയാക്കാൻ '6' ദിവസം വേണം. അതേ ജോലി ഒരു ദിവസം കൊണ്ട്പൂർത്തിയാക്കാൻ എത്ര ആൾക്കാർ വേണം?-
A pipe can fill a tank in 6 hours. Another pipe can empty the filled tank in 30 hours. If both the pipes are opened simultaneously, then the time (in hours) in which the tank will be two-third filled, is
Every Sunday, Rahul jogs 3 miles. If he jogs 1 mile on Monday and each day he jogs 1 mile more than the previous day. How many miles jogs in 2 weeks:
K alone can complete a work in 20 days and M alone can complete the same work in 30 days. K and M start the work together but K leaves the work after 5 days of the starting of work. In how many days M will complete the remaining work?
A and B can do a work together in 18 days. A is three times as efficient as B. In how many days can B alone complete the work?