Jobs going behind the schedule are conveniently shown in

AMilestone chart

BPie chart

CBar chart

DGantt chart

Answer:

D. Gantt chart

Read Explanation:

A Gantt chart is the most suitable chart to illustrate a project schedule. It lists tasks on the vertical axis and time intervals on the horizontal axis. The width of the horizontal bars shows the duration of each activity. Gantt charts depict start and finish dates of elements and the work breakdown structure. They also show dependency relationships and current schedule status using shadings and a vertical "TODAY" line. Milestone, pie and bar charts are different types of charts for data representation.


Related Questions:

The amount of time elapsed from the moment an inventory replenishment order is placed and the moment the supplier delivers the goods is
IF (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Rowan plan, wages for the job will be-
Pallet is an example for which operating principle of material handling plan?
Which of the following layout has the properties of both line and functional layouts
Method study is