Madhu and Shiney together can complete a piece of work in 20 days, Shiney and Rosy together can complete the same work in 12 days, and Rosy and Madhu together can complete the work in 15 days. In how many days will three of them complete it together?

A12 days

B5 days

C15 days

D10 days

Answer:

D. 10 days

Read Explanation:

Madhu and Shiney together can complete the work in =20 days

shiney and rosy can =12

rosy and madhu can =15

LCM of these days are the total work =60

efficiency of Madhu and Shiney=60/20=360/20=3

efficiency of shiney and rosy =60/12=560/12=5

efficiency of rosy and madhu =60/15=460/15=4

2(madhu+shiney+rosy)=5+4+3=122(madhu+shiney+rosy)=5+4+3=12

together they can complete the work in =(60/12)×2=10days=(60/12)\times2=10days


Related Questions:

In what ratio must oil worth Rs. 80/kg is mixed with oil worth Rs. 85/kg and selling the mixture at Rs. 98.25/kg, there can be a profit of 20% ?
Two inlet pipes A and B can fill a cistern in 30 minutes and 36 minutes, respectively. Initially, only A is opened for 10 minutes. After 10 minutes, A is closed and B is opened. In how much time (in minutes) will the inlet pipe B fill the remaining part of the cistern?
A pipe can fill a tank in 6 hours, and another pipe can fill the same tank in 8 hours. If both pipes are opened at the same time, how long (in hours, rounded off to one decimal place) will it take to fill the tank?
12 ആളുകൾ ചേർന്ന് ഒരു ജോലി 15 ദിവസംകൊണ്ട് തീർക്കും. എന്നാൽ അതേ ജോലി 10 ആളുകൾ എത്ര ദിവസം കൊണ്ട് തീർക്കും?
30 പുരുഷന്മാർ 8 മണിക്കൂർ ജോലി ചെയ്യുന്നുവെങ്കിൽ 16 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും, 24 പുരുഷന്മാർ 5 മണിക്കൂർ ജോലി ചെയ്താൽ എത്ര ദിവസം കോണ്ട് ജോലി പൂർത്തിയാക്കാൻ കഴിയും ?