Madhu and Shiney together can complete a piece of work in 20 days, Shiney and Rosy together can complete the same work in 12 days, and Rosy and Madhu together can complete the work in 15 days. In how many days will three of them complete it together?

A12 days

B5 days

C15 days

D10 days

Answer:

D. 10 days

Read Explanation:

Madhu and Shiney together can complete the work in =20 days

shiney and rosy can =12

rosy and madhu can =15

LCM of these days are the total work =60

efficiency of Madhu and Shiney=60/20=360/20=3

efficiency of shiney and rosy =60/12=560/12=5

efficiency of rosy and madhu =60/15=460/15=4

2(madhu+shiney+rosy)=5+4+3=122(madhu+shiney+rosy)=5+4+3=12

together they can complete the work in =(60/12)×2=10days=(60/12)\times2=10days


Related Questions:

A and B can do a piece of work in 28 days and 35 days, respectively. They work on alternate days starting with A till the work gets completed. How long (in days) would it take A and B to complete the work?
A & B together do a work in 40 days. B & C together do in 25 days. A and B started working together, and A left work after 6 days & B left work after 8 days. After A left, C join the work & C completed the work in 40.5 days, C alone can complete the work in how many days?
ഒരു ടാങ്ക് അതിന്റെ 3/4 ഭാഗം വെള്ളം നിറച്ചിരിയ്ക്കുന്നു. 5 ലിറ്റർ വെള്ളം കൂടി ഒഴിച്ചാൽ അതിന്റെ 4/5 ഭാഗം നിറയുമെങ്കിൽ ടാങ്കിന്റെ യഥാർത്ഥ ശേഷി എത്ര ?
Working alone, A can do a job in 15 days and B can do the same job in 18 days. In how many days will the job be completed if both work together?
A can finish painting a sari in 11 days, B in 20 days and C in 55 days, if they work independently. In how many days can the work be completed if A is assisted by B on every odd numbered day and by C on every even numbered day till the work completes?