Madhu and Shiney together can complete a piece of work in 20 days, Shiney and Rosy together can complete the same work in 12 days, and Rosy and Madhu together can complete the work in 15 days. In how many days will three of them complete it together?

A12 days

B5 days

C15 days

D10 days

Answer:

D. 10 days

Read Explanation:

Madhu and Shiney together can complete the work in =20 days

shiney and rosy can =12

rosy and madhu can =15

LCM of these days are the total work =60

efficiency of Madhu and Shiney=60/20=360/20=3

efficiency of shiney and rosy =60/12=560/12=5

efficiency of rosy and madhu =60/15=460/15=4

2(madhu+shiney+rosy)=5+4+3=122(madhu+shiney+rosy)=5+4+3=12

together they can complete the work in =(60/12)×2=10days=(60/12)\times2=10days


Related Questions:

Prakash and Vinesh can complete a certain piece of work in 10 and 8 days, respectively, They started to work together, and after 3 days, Vinesh left. In how many days will Prakash complete the remaining work?
30 പേർ ചേർന്ന് 8 ദിവസം കൊണ്ട് ചെയ്തുതീർക്കുന്ന ഒരു ജോലി 40 പേർ ചേർന്ന് എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?
10 ദിവസം കൊണ്ടാണ് A ഒരു ജോലി പൂർത്തിയാക്കുന്നത്. A 6 ദിവസം ജോലി ചെയ്തു. ശേഷം വിട്ടുപോകുന്നു. ശേഷിക്കുന്ന ജോലി B 2 ദിവസം കൊണ്ട് തീർക്കുന്നു. B ഒറ്റയ്ക്ക് എത്ര ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാക്കും?
Working alone, A can do a job in 15 days and B can do the same job in 18 days. In how many days will the job be completed if both work together?
Tripti can construct a divider alone in 4 days while Rajan can construct it alone in 3 days. If they construct it together and get a payment of Rs. 14000, then what is Tripti's share?