Negative slack occurs when -

AEvents stick to their schedule

BDummy activities are large in number

CActivities lie in critical path

DThere is deficiency of resources

Answer:

D. There is deficiency of resources

Read Explanation:

Negative slack occurs when the latest allowable occurrence time (TL) is less than the earliest expected time (TE), indicating the project is behind schedule due to a lack of resources. Slack time can be calculated using the equation Slack = TL - TE. Positive slack indicates the project is ahead of schedule with excess resources, while zero slack means the project is on schedule with adequate resources.


Related Questions:

Which of the following statement/statements is/are correct?
Customers waiting at a barber shop is an example of queuing model.
For which of the following situations, linear programming can be applied?
In the Simplex method if in pivot column all the entries are negative or zero when choosing leaving variable then
______________ may be defined as any adjustment to the arrow diagram which becomes necessary owing to departure from the project schedule laid down earlier.