Challenger App

No.1 PSC Learning App

1M+ Downloads
P can do a piece of work in 48 days, which Q can do in 18 days. Q worked at it for 15 days. P can finish the remaining work in:

A9 days

B8 days

C6 days

D3 days

Answer:

B. 8 days

Read Explanation:

image.png

Related Questions:

Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?
F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?
15 സ്ത്രീകൾക്ക് 18 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാം. 27 ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാക്കാൻ എത്ര സ്ത്രീകൾ വേണം?
In what ratio must oil worth Rs. 80/kg is mixed with oil worth Rs. 85/kg and selling the mixture at Rs. 98.25/kg, there can be a profit of 20% ?
If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 men do the same work by working 6 hours a day?