If Anil takes 5 days to complete a task when he works for 8 hours a day, how many days will he take to complete the task if he works 6 hours a day?

A6 2/3 days

B7 1/2 days

C7 2/3 days

D6 days

Answer:

A. 6 2/3 days

Read Explanation:

Total work remains constant.

Calculate total work

Total work=5×8=40 hours\text{Total work} = 5 \times 8 = 40 \text{ hours}

Find required days at 6 hours/day

Days=406=623\text{Days} = \frac{40}{6} = 6\tfrac{2}{3}


Days=406=623\text{Days} = \frac{40}{6} = 6\frac{2}{3}


Related Questions:

18 ജോലിക്കാർ 5 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി 6 ദിവസം കൊണ്ടു ചെയ്തു തീർക്കാൻ എത്ര പേർ വേണം?
Madhu and Shiney together can complete a piece of work in 20 days, Shiney and Rosy together can complete the same work in 12 days, and Rosy and Madhu together can complete the work in 15 days. In how many days will three of them complete it together?
Nitin can do a piece of work in 7 hours. Pravin can do it in 21 hours. With the assistance of Rishi, they completed the work in 3 hours. In how many hours can Rishi alone do it?
24 പുരുഷന്മാർക്ക് ഒരു ജോലി 10 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാമെങ്കിൽ 30പേർക്ക് എത്ര ദിവസം വേണ്ടി വരും?
A ഒരു ജോലി 20 ദിവസം എടുത്തു പൂർത്തിയാക്കുന്നു A യും B യും കൂടി ഒരുമിച്ച് ജോലി പൂർത്തീകരിക്കാൻ 12 ദിവസം എടുക്കും എന്നാൽ B മാത്രമായി പ്രസ്തുത ജോലി പൂർത്തീകരിക്കാൻ എത്ര ദിവസം എടുക്കും ?