Challenger App

No.1 PSC Learning App

1M+ Downloads
P works twice as fast as Q. Q alone can complete some work in 12 days. Working together, how long will P and Q take to complete the work?

A8 days

B4 days

C6 days

D10 days

Answer:

B. 4 days

Read Explanation:

1. Find P's work rate:

  • Since P works twice as fast as Q, P can complete the same work in half the time.

  • P alone can complete the work in 12 days / 2 = 6 days.

2. Calculate individual work rates:

  • Q's work rate: Q completes 1/12 of the work per day.

  • P's work rate: P completes 1/6 of the work per day.

3. Calculate combined work rate:

  • Combined work rate = P's work rate + Q's work rate

  • Combined work rate = (1/6) + (1/12) = 3/12 = 1/4

4. Find the time taken together:

  • Time taken to complete the work together = 1 / Combined work rate

  • Time taken = 1 / (1/4) = 4 days

Therefore, working together, P and Q will take 4 days to complete the work.


Related Questions:

45 ആൾക്കാർ ഒരു ദിവസം 12 മണിക്കൂർ ജോലി ചെയ്ത് 30 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കുമെങ്കിൽ 60 ആൾക്കാർ ഒരു ദിവസം പത്തു മണിക്കൂർ വീതം ജോലി ചെയ്താൽ എത്ര ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാക്കും?
Two pipes A and C can fill a tank in 10 hours and 15 hours respectively. If A is open all the time and C is open for 30 minutes, then find the time needed for the tank to be filled.
രാജു ഒരു ജോലി 20 ദിവസം കൊണ്ട് ചെയ്ത് തീർക്കും. ഗോപു അതേ ജോലി ചെയ്യാൻ 30 ദിവസം എടുക്കും. എങ്കിൽ രണ്ടുപേരും ചേർന്നാൽ ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?
A ക്ക് ഒരു ജോലി 6 ദിവസം കൊണ്ടും B ക്ക് 4 ദിവസം കൊണ്ടും ചെയ്യാൻ കഴിയും. രണ്ടുപേരും ഒരുമിച്ച് പ്രവർത്തിച്ചാൽ എത്ര സമയമെടുക്കും?
എ,ബി എന്നി ടാപ്പുകൾക്ക് യഥാക്രമം 6 മണിക്കൂറും 10 മണിക്കൂറും കൊണ്ട് ഒരു ടാങ്ക് നിറയ്ക്കുവാൻ കഴിയും .എന്നാൽ ടാങ്കിലെ C എന്നദ്വാരം 8 മണിക്കൂർ സമയം കൊണ്ട് നിറഞ്ഞ ടാങ്കിനെ ശൂന്യമാകും.ഒഴിഞ്ഞ ടാങ്കിൽ ദ്വാരം C തുറന്ന് കിടക്കുമ്പോൾ 2 ടാപ്പുകളും ഒരുമിച്ച് തുറന്നാൽ എത്ര സമയം കൊണ്ട് ടാങ്ക് നിറയും ?