Challenger App

No.1 PSC Learning App

★
★
★
★
★
1M+ Downloads
P works twice as fast as Q. Q alone can complete some work in 12 days. Working together, how long will P and Q take to complete the work?

A8 days

B4 days

C6 days

D10 days

Answer:

B. 4 days

Read Explanation:

1. Find P's work rate:

  • Since P works twice as fast as Q, P can complete the same work in half the time.

  • P alone can complete the work in 12 days / 2 = 6 days.

2. Calculate individual work rates:

  • Q's work rate: Q completes 1/12 of the work per day.

  • P's work rate: P completes 1/6 of the work per day.

3. Calculate combined work rate:

  • Combined work rate = P's work rate + Q's work rate

  • Combined work rate = (1/6) + (1/12) = 3/12 = 1/4

4. Find the time taken together:

  • Time taken to complete the work together = 1 / Combined work rate

  • Time taken = 1 / (1/4) = 4 days

Therefore, working together, P and Q will take 4 days to complete the work.


Related Questions:

ജോണിക്ക് 40 ദിവസം കൊണ്ടും രാജുവിന് 48 ദിവസം കൊണ്ടും ബോബിക്ക് 60 ദിവസം കൊണ്ടും ഒരു ജോലി തീർക്കാൻ കഴിയും. അവർ 4 ദിവസം ഒരുമിച്ച് ജോലി ചെയ്തു. തുടർന്ന് രാജു പോയി. അതിനുശേഷം ജോണിയും ബോബിയും 12 ദിവസം ഒരുമിച്ച് ജോലി ചെയ്ത ശേഷം ജോണി പോയി. ബോബിയുടെ ജോലി പൂർത്തിയാക്കാൻ എത്ര ദിവസമെടുക്കും ?
ഒരാൾ 5 ദിവസംകൊണ്ട് 200 വാഴപ്പഴം കഴിച്ചു.ഓരോ ദിവസവും തലേദിവസത്തേക്കാൾ 10 എണ്ണം കൂടുതൽ കഴിച്ചുവെങ്കിൽ അയാൾ ആദ്യ ദിവസം എത്ര വാഴപ്പഴം കഴിച്ചു ?
Two pipes A and B can fill a cistern in 36 minutes and 48 minutes, respectively. Both the pipes are opened at the same time and pipe B is closed after some time. If the cistern gets filled in half an hour, then after how many minutes was pipe B closed?
Vijay can do a piece of work in 4 hours. Ajay can do it in 28 hours. With the assistance of Amit, they completed the work in 3 hours. In how many hours can Amit alone do it?
A ഒരു ജോലി 10 ദിവസം കൊണ്ടും B അതേ ജോലി 15 ദിവസം കൊണ്ടും ചെയ്യുന്നു. A യും B യും കൂടി അതേ ജോലി തീർക്കാൻ എത്ര ദിവസം വേണം?