App Logo

No.1 PSC Learning App

1M+ Downloads
P works twice as fast as Q. Q alone can complete some work in 12 days. Working together, how long will P and Q take to complete the work?

A8 days

B4 days

C6 days

D10 days

Answer:

B. 4 days

Read Explanation:

1. Find P's work rate:

  • Since P works twice as fast as Q, P can complete the same work in half the time.

  • P alone can complete the work in 12 days / 2 = 6 days.

2. Calculate individual work rates:

  • Q's work rate: Q completes 1/12 of the work per day.

  • P's work rate: P completes 1/6 of the work per day.

3. Calculate combined work rate:

  • Combined work rate = P's work rate + Q's work rate

  • Combined work rate = (1/6) + (1/12) = 3/12 = 1/4

4. Find the time taken together:

  • Time taken to complete the work together = 1 / Combined work rate

  • Time taken = 1 / (1/4) = 4 days

Therefore, working together, P and Q will take 4 days to complete the work.


Related Questions:

Two pipes A and C can fill a tank in 10 hours and 15 hours respectively. If A is open all the time and C is open for 30 minutes, then find the time needed for the tank to be filled.
A can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in.
ഒരു പ്രത്യേക ജോലി 2 പുരുഷന്മാർക്ക് 10 ദിവസം കൊണ്ടും 5 സ്ത്രീകൾക്ക് 8 ദിവസം കൊണ്ടുംപൂർത്തിയാക്കാൻ കഴിയും. എങ്കിൽ 1 പുരുഷനും 2 സ്ത്രീകളും ചേർന്ന് പ്രസ്തുത ജോലി എത്ര ദിവസംകൊണ്ട് പൂർത്തിയാക്കാൻ കഴിയും ?
If 3 men or 4 women can plough a field in 43 days, how long will 7 men and 5 women take to plough it ?
3 പുരുഷന്മാരും 4 ആൺകുട്ടികളും ഒരു ജോലി 8 ദിവസം കൊണ്ടു ചെയ്തു തീർക്കും അതേ ജോലി 4 പുരുഷന്മാരും 4 ആൺകുട്ടികളും 6 ദിവസം കൊണ്ടു ചെയ്തു തീർക്കും എങ്കിൽ 2 പുരുഷന്മാരും 4 ആൺകുട്ടികളും ഇതേ ജോലി എത്ര ദിവസം കൊണ്ടു ചെയ്തു തീർക്കും?