App Logo

No.1 PSC Learning App

1M+ Downloads
P works twice as fast as Q. Q alone can complete some work in 12 days. Working together, how long will P and Q take to complete the work?

A8 days

B4 days

C6 days

D10 days

Answer:

B. 4 days

Read Explanation:

1. Find P's work rate:

  • Since P works twice as fast as Q, P can complete the same work in half the time.

  • P alone can complete the work in 12 days / 2 = 6 days.

2. Calculate individual work rates:

  • Q's work rate: Q completes 1/12 of the work per day.

  • P's work rate: P completes 1/6 of the work per day.

3. Calculate combined work rate:

  • Combined work rate = P's work rate + Q's work rate

  • Combined work rate = (1/6) + (1/12) = 3/12 = 1/4

4. Find the time taken together:

  • Time taken to complete the work together = 1 / Combined work rate

  • Time taken = 1 / (1/4) = 4 days

Therefore, working together, P and Q will take 4 days to complete the work.


Related Questions:

ജോണും ദീപുവും ചേർന്ന് ഒരു ജോലി ചെയ്തു തീർക്കാൻ 45 ദിവസം എടുക്കുന്നു.എന്നാൽ ജോൺ ഒറ്റയ്ക്ക് ഈ ജോലി 70 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും. ദീപു ഒറ്റയ്ക്ക്ഇതേ ജോലി ചെയ്തു തീർക്കാൻ എത്ര ദിവസം എടുക്കും?
9 men and 12 women can complete a work in 4 days, whereas 3 men and 6 women can complete it in 10 days. The number of days in which 15 women will complete the work is:
A, B, C എന്നിവരുടെ കാര്യക്ഷമത ആനുപാതികമായി 2: 3: 5 ആണ്. Aക്ക് 50 ദിവസത്തിനുള്ളിൽ ഒരു പ്രവൃത്തി പൂർത്തിയാക്കാൻ കഴിയും. എല്ലാവരും 5 ദിവസം ഒരുമിച്ച് പ്രവർത്തിക്കുന്നു, തുടർന്ന് C ജോലി ഉപേക്ഷിച്ചു, A, B എന്നിവർക്ക് ഒരുമിച്ച് എത്ര ദിവസത്തിനുള്ളിൽ ശേഷിക്കുന്ന ജോലി പൂർത്തിയാക്കാൻ കഴിയും?
Two pipes can fill a tank in 30 hours and 40 hours, respectively. Find the time (in hours) taken to fill the tank when both the pipes are opened simultaneously.
If 16 men or 20 women can do a piece of work in 25 days. In what time will 28 men and 15 women do it?