App Logo

No.1 PSC Learning App

1M+ Downloads
P works twice as fast as Q. Q alone can complete some work in 12 days. Working together, how long will P and Q take to complete the work?

A8 days

B4 days

C6 days

D10 days

Answer:

B. 4 days

Read Explanation:

1. Find P's work rate:

  • Since P works twice as fast as Q, P can complete the same work in half the time.

  • P alone can complete the work in 12 days / 2 = 6 days.

2. Calculate individual work rates:

  • Q's work rate: Q completes 1/12 of the work per day.

  • P's work rate: P completes 1/6 of the work per day.

3. Calculate combined work rate:

  • Combined work rate = P's work rate + Q's work rate

  • Combined work rate = (1/6) + (1/12) = 3/12 = 1/4

4. Find the time taken together:

  • Time taken to complete the work together = 1 / Combined work rate

  • Time taken = 1 / (1/4) = 4 days

Therefore, working together, P and Q will take 4 days to complete the work.


Related Questions:

If A can complete a job in 15 days and B can complete the same job in 20 days, then how many days (rounded up to the nearest two decimal places) will it take for both A and B to complete the job together?
A, B, C can together complete the work in 12 days. If A is thrice faster than B, and B is twice faster than C, B alone can do the work in:
A Pipe can fill a tank in 10 hours. Due to leak in the bottom it fills the tank in 30 hours. If the tank is full, how much time will the leak take to empty it
15 സ്ത്രീകൾക്ക് 18 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാം. 27 ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാക്കാൻ എത്ര സ്ത്രീകൾ വേണം?
If P and Q together can do a job in 15 days, Q and R together can do it in 12 days and P and R together can do the same in 20 days, then in how many days will the job be completed, if all the three work together?