Challenger App

No.1 PSC Learning App

1M+ Downloads
P works twice as fast as Q. Q alone can complete some work in 12 days. Working together, how long will P and Q take to complete the work?

A8 days

B4 days

C6 days

D10 days

Answer:

B. 4 days

Read Explanation:

1. Find P's work rate:

  • Since P works twice as fast as Q, P can complete the same work in half the time.

  • P alone can complete the work in 12 days / 2 = 6 days.

2. Calculate individual work rates:

  • Q's work rate: Q completes 1/12 of the work per day.

  • P's work rate: P completes 1/6 of the work per day.

3. Calculate combined work rate:

  • Combined work rate = P's work rate + Q's work rate

  • Combined work rate = (1/6) + (1/12) = 3/12 = 1/4

4. Find the time taken together:

  • Time taken to complete the work together = 1 / Combined work rate

  • Time taken = 1 / (1/4) = 4 days

Therefore, working together, P and Q will take 4 days to complete the work.


Related Questions:

5 men and 6 women can do a piece of work in 6 days while 3 men and 5 women can do the same work in 9 days. In how many days can 3 men and 2 women do the same work?
A, B, C can together complete the work in 12 days. If A is thrice faster than B, and B is twice faster than C , B alone can do the work in :
A man, a woman and a boy can complete a work in 20 days, 30 days and 60 days respectively. How many boys must assist 2 men and 8 women so as to complete the work in 2 days?
A and B together can do a certain work in x days. Working alone, A and B can do the same work in (x + 8) and (x + 18) days, respectively. A and B together will complete 5/6 of the same work in:
അജയൻ ഒരു ജോലി 2 മണിക്കുറും അരുൺ 6 മണിക്കൂറും ചെയ്തു. രണ്ട് പേർക്കും കൂടി ലഭിച്ച കൂലി 800 രൂപയാണ്. ഈ തുക എങ്ങനെയാണ് വീതിക്കേണ്ടത് ?