Challenger App

No.1 PSC Learning App

1M+ Downloads
P works twice as fast as Q. Q alone can complete some work in 12 days. Working together, how long will P and Q take to complete the work?

A8 days

B4 days

C6 days

D10 days

Answer:

B. 4 days

Read Explanation:

1. Find P's work rate:

  • Since P works twice as fast as Q, P can complete the same work in half the time.

  • P alone can complete the work in 12 days / 2 = 6 days.

2. Calculate individual work rates:

  • Q's work rate: Q completes 1/12 of the work per day.

  • P's work rate: P completes 1/6 of the work per day.

3. Calculate combined work rate:

  • Combined work rate = P's work rate + Q's work rate

  • Combined work rate = (1/6) + (1/12) = 3/12 = 1/4

4. Find the time taken together:

  • Time taken to complete the work together = 1 / Combined work rate

  • Time taken = 1 / (1/4) = 4 days

Therefore, working together, P and Q will take 4 days to complete the work.


Related Questions:

മനുവിന് ഒരു ജോലി ചെയ്യാൻ 10 ദിവസം വേണം അനുവിന് അത് ചെയ്ത് തീർക്കാൻ 15 ദിവസം വേണം. എങ്കിൽ രണ്ടു പേരും ചേർന്ന് ഈ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും?
A and B together can work in 6 days. A alone 8 days. In how many days B alone do it?
Tripti can construct a divider alone in 4 days while Rajan can construct it alone in 3 days. If they construct it together and get a payment of Rs. 14000, then what is Tripti's share?
Thirty men can complete a work in 36 days. In how many days can 18 men complete the same piece of work?
Abhay and Bharat can complete a certain piece of work in 9 and 11 days, respectively, They started to work together, and after 3 days, Bharat left. In how many days will Abhay complete the remaining work?