Challenger App

No.1 PSC Learning App

1M+ Downloads
P works twice as fast as Q. Q alone can complete some work in 12 days. Working together, how long will P and Q take to complete the work?

A8 days

B4 days

C6 days

D10 days

Answer:

B. 4 days

Read Explanation:

1. Find P's work rate:

  • Since P works twice as fast as Q, P can complete the same work in half the time.

  • P alone can complete the work in 12 days / 2 = 6 days.

2. Calculate individual work rates:

  • Q's work rate: Q completes 1/12 of the work per day.

  • P's work rate: P completes 1/6 of the work per day.

3. Calculate combined work rate:

  • Combined work rate = P's work rate + Q's work rate

  • Combined work rate = (1/6) + (1/12) = 3/12 = 1/4

4. Find the time taken together:

  • Time taken to complete the work together = 1 / Combined work rate

  • Time taken = 1 / (1/4) = 4 days

Therefore, working together, P and Q will take 4 days to complete the work.


Related Questions:

60 ആളുകൾ 15 ദിവസം കൊണ്ട് തീർക്കുന്ന ജോലി 12 ദിവസം കൊണ്ട് തീർക്കണമെങ്കിൽ എത്ര പേരെ കൂടുതൽ നിയമിക്കണം ?
Ravi can complete one-fourth of the total work in 15 days, Chavi can complete one-third of the total work in 18 days, Dhani can complete half of the total work in 24 days. In how much time can Ravi, Chavi and Dhani complete three-fourth of the work together?
A and B together can do a piece of work in 12 days and A alone can complete the work in 18 days how long will B alone take to complete the job ?
60 ആളുകൾ 10 ദിവസം കൊണ്ട് തീർക്കുന്ന ജോലി 6 ദിവസം കൊണ്ട് തീർക്കാൻ എത്ര ആളുകൾ അധികം വേണ്ടിവരും ?
ഒരാൾ ഒരു ദിവസം കൊണ്ട് 2 മീറ്റർ × 2 മീറ്റർ × 2 മീറ്റർ സൈസിൽ ഒരു കുഴി നിർമ്മിക്കും. ഇതേ നിരക്കിൽ 3 പേർ ചേർന്ന് 4 മീറ്റർ × 4 മീറ്റർ × 4 മീറ്റർ സൈസിൽ ഒരു കുഴി നിർമ്മിക്കാൻ എത്ര ദിവസം വേണം?