Challenger App

No.1 PSC Learning App

1M+ Downloads
P works twice as fast as Q. Q alone can complete some work in 12 days. Working together, how long will P and Q take to complete the work?

A8 days

B4 days

C6 days

D10 days

Answer:

B. 4 days

Read Explanation:

1. Find P's work rate:

  • Since P works twice as fast as Q, P can complete the same work in half the time.

  • P alone can complete the work in 12 days / 2 = 6 days.

2. Calculate individual work rates:

  • Q's work rate: Q completes 1/12 of the work per day.

  • P's work rate: P completes 1/6 of the work per day.

3. Calculate combined work rate:

  • Combined work rate = P's work rate + Q's work rate

  • Combined work rate = (1/6) + (1/12) = 3/12 = 1/4

4. Find the time taken together:

  • Time taken to complete the work together = 1 / Combined work rate

  • Time taken = 1 / (1/4) = 4 days

Therefore, working together, P and Q will take 4 days to complete the work.


Related Questions:

A ഒരു ജോലി 8 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്നു. അതേ ജോലി B, 10 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും. എന്നാൽ A യും B യും ചേർന്ന് ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാം?
A യും B യും ചേർന്ന് 24 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാൻ കഴിയും. 40 ദിവസത്തിനുള്ളിൽ A ക്ക് തനിച്ച് ഈ ജോലി ചെയ്യാൻ കഴിയും. എത്ര ദിവസത്തിനുള്ളിൽ B ഒറ്റയ്ക്ക് ജോലി ചെയ്തു തീർക്കും ?
6 മിനിട്ടുകൊണ്ട് ഒരു ടാങ്കിന്റെ 3/5 ഭാഗം നിറഞ്ഞു. ഇനി നിറയാൻ എത്ര മിനിട്ടു വേണം ?
16 പുരുഷന്മാർക്ക് 30 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും . 24 പുരുഷന്മാർ എത്ര ദിവസം കൊണ്ട് ആ ജോലി പൂർത്തിയാക്കും ?
Abhay and Bharat can complete a certain piece of work in 9 and 11 days, respectively, They started to work together, and after 3 days, Bharat left. In how many days will Abhay complete the remaining work?