A point which represents either starting or termination of activity is known as -

Aloop

Bnetwork

Cevent

Dalgorithm

Answer:

C. event

Read Explanation:

An event, denoted by nodal points, marks the start and completion of an activity in a project network. A point representing the start or termination of an activity is called an event. The graphical representation of activities and events is called a network, which depicts the relationship between different activities in a logical sequence using arrows