Which of the following input data are needed for MRP?

  1. Master production schedule
  2. Inventory position
  3. Machine capacity
  4. Bill of materials

    Ai only

    Bi, ii, iv

    Cii, iii

    DNone of these

    Answer:

    B. i, ii, iv

    Read Explanation:

    Materials Requirements Planning (MRP) system needs three major input components: Master production schedule (MPS), Inventory status file, and Bill of Materials (BOM). MPS is designed to meet the future market demand. BOM represents the product structure while the inventory status file keeps an up-to-date record of each item in the inventory.