Fulkerson's rule is used for numbering events in a project scheduling network. In this context, every activity in the network is assigned a name or symbol. The events are represented by circles at the beginning and end of each activity and are assigned numbers. This numbering system assists in accurately drawing the network. The numbers should be assigned to reflect the logical sequence of events in the network.