App Logo

No.1 PSC Learning App

1M+ Downloads
Raj alone can do a piece of work in 8 days. Raman alone can do it in 12 days. If the total wage for the work is Rs. 500. How much should Raj be paid if they work together for the entire duration of the work?

A270

B210

C390

D300

Answer:

D. 300

Read Explanation:

Solution: We know that ratio of the wages will be the inverse of the ratio of the number of days required by each to do the work ⇒ Ratio of wages of Raj and Raman = 1/8 : 1/12 = 12 : 8 Let the wage of Raj be 12x and Raman be 8x ⇒ 12x + 8x = 500 ⇒ 20x = 500 ⇒ x = 25 ∴ Raj gets 12x = 12 × 25 = 300


Related Questions:

A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work?
A fruit vendor restocks apples every 4 days and bananas every 6 days. If he restocks both fruits today, after how many days will he restock both apples and bananas on the same day again?
8 പുരുഷന്മാരും 2 സ്ത്രീകളും ചേർന്ന് 24 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. 16 പുരുഷന്മാർ 8 മണിക്കൂറിനുള്ളിൽ ചെയ്യുന്ന ജോലി 24 മണിക്കൂറിനുള്ളിൽ 2 സ്ത്രീകൾ ചെയ്യുന്ന ജോലിക്ക് തുല്യമാണെങ്കിൽ, 40 പുരുഷന്മാരും 45 സ്ത്രീകളും ചേർന്ന് എത്ര സമയം കൊണ്ട് 1.5 മടങ്ങ് ജോലി പൂർത്തിയാക്കും?
If 200 men can dig a canal working for 8 hours a day in 6 days, how long will it take to dig the canal, if 300 men work 6 hours per day?
A and B undertake to complete a piece of work for ₹600. A alone can complete it in 4 days while B alone can complete it in 6 days. With the help of C, they finish the work in 2 days. Find the share of C in the payment received.