App Logo

No.1 PSC Learning App

1M+ Downloads
Raju and Raman can complete a piece of work in 12 days and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days will the work be completed?

A$$13\frac23$ days$

B$$13\frac13$ days$

C$$14\frac23$ days$

D$$14\frac13$ days$

Answer:

$$13\frac23$ days$

Read Explanation:

raju =12 days

raman 16 days

total work is the LCM=48

efficiency(one day work) of raju =48/12=4

efficiency(one day work) of raman =48/16=3

alternate days work start with raju

4,3,4,3,4,3,....

for 13 days the work is 46 then the next work is raman

one day work of raju is 3 but the work left is 2 so the work is 2/3

so the total work days is 13 and 2/3 days


Related Questions:

A and B together can do a piece of work in 12 days and A alone can complete the work in 18 days how long will B alone take to complete the job ?
ശശിയും സോമനും കൂടി ഒരു ജോലി 12 ദിവസം കൊണ്ട് തീർക്കും. ശശിക്ക് ഒറ്റയ്ക്ക് ആ ജോലി തീർക്കാൻ 20 ദിവസം വേണമെങ്കിൽ സോമന് ആ ജോലി തീർക്കാൻ എത്ര ദിവസം വേണം?
6 പേർ 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കുന്നു. എങ്കിൽ 8 പേർ എത്ര ദിവസംകൊണ്ട് ആ ജോലി പൂർത്തീകരിക്കും ?
A യും B യും ചേർന്ന് ഒരു ജോലി ഏഴു ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും . A യ്ക്ക് B യുടെ 1 3/4 മടങ്ങ് കാര്യക്ഷമതയുണ്ട് അതേ ജോലി A യ്ക്ക് മാത്രം എത്ര ദിവസം കൊണ്ട് ചെയ്യാൻ കഴിയും ?
60 ആളുകൾ 15 ദിവസം കൊണ്ട് തീർക്കുന്ന ജോലി 12 ദിവസം കൊണ്ട് തീർക്കണമെങ്കിൽ എത്ര പേരെ കൂടുതൽ നിയമിക്കണം ?