App Logo

No.1 PSC Learning App

1M+ Downloads
Raju and Raman can complete a piece of work in 12 days and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days will the work be completed?

A$$13\frac23$ days$

B$$13\frac13$ days$

C$$14\frac23$ days$

D$$14\frac13$ days$

Answer:

$$13\frac23$ days$

Read Explanation:

raju =12 days

raman 16 days

total work is the LCM=48

efficiency(one day work) of raju =48/12=4

efficiency(one day work) of raman =48/16=3

alternate days work start with raju

4,3,4,3,4,3,....

for 13 days the work is 46 then the next work is raman

one day work of raju is 3 but the work left is 2 so the work is 2/3

so the total work days is 13 and 2/3 days


Related Questions:

10 ആളുകൾക്ക് ഒരു ജോലി ചെയ്യാൻ 8 ദിവസം വേണം. അതേ ജോലി ചെയ്യാൻ 20 ആളുകൾക്ക് എത്ര ദിവസം വേണം ?
A cistern has a leak which would empty it in 8 hours.A tap is turned on which admits 6 litres a minute in the cistern, and it is now emptied in 12 hours. How many litres does the cistern hold?
A, B, C എന്നിവരുടെ കാര്യക്ഷമത ആനുപാതികമായി 2: 3: 5 ആണ്. Aക്ക് 50 ദിവസത്തിനുള്ളിൽ ഒരു പ്രവൃത്തി പൂർത്തിയാക്കാൻ കഴിയും. എല്ലാവരും 5 ദിവസം ഒരുമിച്ച് പ്രവർത്തിക്കുന്നു, തുടർന്ന് C ജോലി ഉപേക്ഷിച്ചു, A, B എന്നിവർക്ക് ഒരുമിച്ച് എത്ര ദിവസത്തിനുള്ളിൽ ശേഷിക്കുന്ന ജോലി പൂർത്തിയാക്കാൻ കഴിയും?
Vijayan can do a job in 25 days and Achyuth can do it in 20 days. Vijayan started the work and Achyuth joined af. ter 15 days and Vijayan left. How many days did Achyuth take to complete the ramaining job?
Robert takes twice as much time as Tom and thrice as much time as George to complete a work. If working together, they can complete it in 23 hours, then find the time that Tom will take to complete the work.