Challenger App

No.1 PSC Learning App

1M+ Downloads
Raju and Raman can complete a piece of work in 12 days and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days will the work be completed?

A$$13\frac23$ days$

B$$13\frac13$ days$

C$$14\frac23$ days$

D$$14\frac13$ days$

Answer:

$$13\frac23$ days$

Read Explanation:

raju =12 days

raman 16 days

total work is the LCM=48

efficiency(one day work) of raju =48/12=4

efficiency(one day work) of raman =48/16=3

alternate days work start with raju

4,3,4,3,4,3,....

for 13 days the work is 46 then the next work is raman

one day work of raju is 3 but the work left is 2 so the work is 2/3

so the total work days is 13 and 2/3 days


Related Questions:

Amit can complete a piece of work in 120 days. Amit and Sejal can complete the same work in 72 days. They started together but Sejal left after working for 20 days. Find the approximate number of days in which Amit will complete the remaining work.
രാജു ഒരു ജോലി 20 ദിവസം കൊണ്ട് ചെയ്ത് തീർക്കും. ഗോപു അതേ ജോലി ചെയ്യാൻ 30 ദിവസം എടുക്കും. എങ്കിൽ രണ്ടുപേരും ചേർന്നാൽ ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?
16 ആളുകൾ 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കും. ഈ ജോലി 8 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ എത്ര ആളുകൾ കൂടുതലായി വേണം ?
A pipe can fill a tank in 6 hours. Another pipe can empty the filled tank in 30 hours. If both the pipes are opened simultaneously, then the time (in hours) in which the tank will be two-third filled, is
എയ്ക്ക് മാത്രം 10 ദിവസത്തിനുള്ളിൽ പദ്ധതി പൂർത്തിയാക്കാൻ കഴിയും; ബിക്ക് മാത്രം 20 ദിവസം കൊണ്ട് പൂര് ത്തിയാക്കാന് കഴിയും, സിക്ക് മാത്രം 30 ദിവസം കൊണ്ട് പൂര് ത്തിയാക്കാന് കഴിയും. 1,100 രൂപയാണ് ഇവര് ഒരുമിച്ച് ഈ പദ്ധതിക്കായി സമ്പാദിക്കുന്നത്. A യുടെയും C യുടെയും മൊത്തം വരുമാനം B യുടെ വരുമാനത്തെക്കാൾ എത്രയാണ്?