Challenger App

No.1 PSC Learning App

1M+ Downloads
Raju and Raman can complete a piece of work in 12 days and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days will the work be completed?

A$$13\frac23$ days$

B$$13\frac13$ days$

C$$14\frac23$ days$

D$$14\frac13$ days$

Answer:

$$13\frac23$ days$

Read Explanation:

raju =12 days

raman 16 days

total work is the LCM=48

efficiency(one day work) of raju =48/12=4

efficiency(one day work) of raman =48/16=3

alternate days work start with raju

4,3,4,3,4,3,....

for 13 days the work is 46 then the next work is raman

one day work of raju is 3 but the work left is 2 so the work is 2/3

so the total work days is 13 and 2/3 days


Related Questions:

4 men and 3 women finish a job in 6 days, and 5 men and 7 women can do the same job in 4 days. How long will 8 men and 6 women take to do the same job?
20 women can complete a work in 15 days. 16 men can complete the same work in 15 days. Find the ratio between the work efficiency of a man to a woman.
A and B together can do a piece of work in 12 days and A alone can complete the work in 18 days how long will B alone take to complete the job ?
A and B together can finish a work in 16 days, while B can do the same work alone in 24 days. In how many days can A alone finish the work ?
3 പുരുഷന്മാരും 4 ആൺകുട്ടികളും ഒരു ജോലി 8 ദിവസം കൊണ്ടു ചെയ്തു തീർക്കും അതേ ജോലി 4 പുരുഷന്മാരും 4 ആൺകുട്ടികളും 6 ദിവസം കൊണ്ടു ചെയ്തു തീർക്കും എങ്കിൽ 2 പുരുഷന്മാരും 4 ആൺകുട്ടികളും ഇതേ ജോലി എത്ര ദിവസം കൊണ്ടു ചെയ്തു തീർക്കും?