Challenger App

No.1 PSC Learning App

1M+ Downloads
Raju and Raman can complete a piece of work in 12 days and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days will the work be completed?

A$$13\frac23$ days$

B$$13\frac13$ days$

C$$14\frac23$ days$

D$$14\frac13$ days$

Answer:

$$13\frac23$ days$

Read Explanation:

raju =12 days

raman 16 days

total work is the LCM=48

efficiency(one day work) of raju =48/12=4

efficiency(one day work) of raman =48/16=3

alternate days work start with raju

4,3,4,3,4,3,....

for 13 days the work is 46 then the next work is raman

one day work of raju is 3 but the work left is 2 so the work is 2/3

so the total work days is 13 and 2/3 days


Related Questions:

Pipes A and B can empty a full tank in 5 hours and 12 hours respectively. Pipe C can fill the same empty tank in 2 hours. If all the three pipes are opened together, then the tank will be filled in:
A യ്ക്ക് 10 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. B ക്ക് 15 ദിവസം കൊണ്ട് ഇതേ ജോലി പൂർത്തിയാക്കാൻ കഴിയും. അവർ ഒരുമിച്ച് പ്രവർത്തിച്ചാൽ എത്ര ദിവസം കൊണ്ട് പണി പൂർത്തിയാകും?
6 പേർ 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കുന്നു. എങ്കിൽ 8 പേർ എത്ര ദിവസംകൊണ്ട് ആ ജോലി പൂർത്തീകരിക്കും ?
3 സ്ത്രീകൾക്കും 6 പുരുഷൻമാർക്കും കൂടി ഒരു എംബ്രോയിഡറി ജോലി 5 ദിവസം കൊണ്ട് തീർക്കുവാനാകും. അതുപോലെ 4 സ്ത്രീകൾക്കും 7 പുരുഷന്മാർക്കും കൂടി 4 ദിവസം കൊണ്ട്തീർക്കുവാനാകും. എന്നാൽ ഒരു സ്ത്രീ മാത്രം ജോലി ചെയ്താലും ഒരു പുരുഷൻ മാത്രം ചെയ്താലും ജോലി തീർക്കാൻ എടുക്കുന്ന ദിവസം യഥാക്രമം
30 പേർ ചേർന്ന് 8 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി 40 പേർ ചേർന്ന് എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?