App Logo

No.1 PSC Learning App

1M+ Downloads
Raju and Raman can complete a piece of work in 12 days and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days will the work be completed?

A$$13\frac23$ days$

B$$13\frac13$ days$

C$$14\frac23$ days$

D$$14\frac13$ days$

Answer:

$$13\frac23$ days$

Read Explanation:

raju =12 days

raman 16 days

total work is the LCM=48

efficiency(one day work) of raju =48/12=4

efficiency(one day work) of raman =48/16=3

alternate days work start with raju

4,3,4,3,4,3,....

for 13 days the work is 46 then the next work is raman

one day work of raju is 3 but the work left is 2 so the work is 2/3

so the total work days is 13 and 2/3 days


Related Questions:

A pipe can fill the tank in 10 minutes and another pipe can empty it in 12 minutes. If both the pipes are opened the time in which the tank is filled
A , B എന്നിവർക്ക് യഥാക്രമം 15 ദിവസവും 10 ദിവസവും ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. അവർ ഒരുമിച്ച് ജോലി ചെയ്യാൻ തുടങ്ങി, പക്ഷേ 2 ദിവസത്തിന് ശേഷം Bക്ക് പോകേണ്ടി വന്നു, A മാത്രം ബാക്കിയുള്ള ജോലി പൂർത്തിയാക്കി. A പണി പൂർത്തിയാക്കാൻ എത്ര ദിവസം എടുക്കും?
16 ആളുകൾ 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കും. ഈ ജോലി 8 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ എത്ര ആളുകൾ കൂടുതലായി വേണം ?
ഒരു പുരുഷനും സ്ത്രീക്കും അവർ ഒരുമിച്ച് ചെയ്ത ജോലികൾക്ക് 20 ദിവസത്തേക്ക് 1500 രൂപ വേതനം ലഭിച്ചു. പുരുഷന്റെ കാര്യക്ഷമത സ്ത്രീയുടേതിനേക്കാൾ ഇരട്ടിയാണെങ്കിൽ, സ്ത്രീയുടെ ദൈനംദിന വേതനം കണ്ടെത്തുക?
രാമു ഒരു ജോലി 6 ദിവസം കൊണ്ട് ചെയ്യും. രമ അതേ ജോലി ചെയ്യാൻ 8 ദിവസം എടുക്കും. എന്നാൽ രണ്ടുപേരും ഒരുമിച്ച് ജോലി ചെയ്താൽ ജോലി തീർക്കാൻ എത്ര ദിവസം വേണം ?