Challenger App

No.1 PSC Learning App

1M+ Downloads
Raju and Raman can complete a piece of work in 12 days and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days will the work be completed?

A$$13\frac23$ days$

B$$13\frac13$ days$

C$$14\frac23$ days$

D$$14\frac13$ days$

Answer:

$$13\frac23$ days$

Read Explanation:

raju =12 days

raman 16 days

total work is the LCM=48

efficiency(one day work) of raju =48/12=4

efficiency(one day work) of raman =48/16=3

alternate days work start with raju

4,3,4,3,4,3,....

for 13 days the work is 46 then the next work is raman

one day work of raju is 3 but the work left is 2 so the work is 2/3

so the total work days is 13 and 2/3 days


Related Questions:

Six typists can type a given data in 16 days. How many days will 4 typists take to do the same work?
After 60 litres of petrol was poured into an empty storage tank, it was still 10% empty. How much petrol (in litres, rounded off to two decimal place) must be poured into the storage tank in order to fill it?
10 പുരുഷന്മാർ ഒരു ജോലി 12 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാൻ കഴിയുമെങ്കിൽ അതെ ജോലി ചെയ്യാൻ 12 പുരുഷന്മാർ എടുക്കുന്ന സമയം എത്ര?
A can do a piece of work in 10 days. B can do it in 15 days. With the assistance of C, they completed the work in 2 days. C alone can do it in ______________days.
51 men can complete a work in 12 days. Four days after they started working 6 more men joined them. How many days will they now take to complete the remaining work?