Ramanan and Shyam together can do a work in 8 days. Both of B them began to work. After 3 days Ramanan fell ill, Shyam completed the remaining work in 15 days. In how many days can Ramanan complete the work?

A12

B15

C16

D17

Answer:

A. 12


Related Questions:

Six typists can type a given data in 16 days. How many days will 4 typists take to do the same work?
C alone can complete a work in 20 days and D alone can complete the same work in 30 days. In how many days C and D together can complete the same work?
A and B together can do a certain work in x days. Working alone, A and B can do the same work in (x + 8) and (x + 18) days, respectively. A and B together will complete 5/6 of the same work in:
A can do a piece of work in 30 days, while B alone can do it in 40 days. In how many days can A and B working together do it?
A, B, and C can do a work separately in 18, 36 and 54 days, respectively. They started the work together, but B and C left 5 days and 10 days, respectively, before the completion of the work. In how many days was the work finished?