App Logo

No.1 PSC Learning App

1M+ Downloads
If Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?

A96 days

B128 days

C64 days

D118 days

Answer:

B. 128 days

Read Explanation:

Solution: Given: Rohit alone can complete one-fourth of a work in 32 days Formula used: (M × D × H/W = constant Where, M = number of person D = number of days H = number of hours W = work done Also, Work is directly proportional to days Calculation: One-fourth of the work can be completed in 32 days Then, Complete work will be completed in 32 × 4 = 128 days


Related Questions:

Ratul can do a piece of work in 24 days and Amal can do the same work in 32 days. They worked together for 8 days and then Amal left. How much time (in days ) will Ratul, working alone, take to complete the remaining work?
A can do a certain work in 18 days. B is 25% less efficient than A. A alone worked for a few days and then, B joined him. Both worked together till the completion of the work. The entire work got completed in 12 days. For how many days did A and B work together?
16 ആളുകൾ 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കും. ഈ ജോലി 8 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ എത്ര ആളുകൾ കൂടുതലായി വേണം ?
A can do a piece of work in 12 days and B can do it in 18 days. They work together for 2 days and then A leaves. How long will B take to finish the remaining work ?
ഒരു ജോലി ചെയ്ത് തീർക്കാൻ 16 പേർക്ക് 30 ദിവസം വേണം. എന്നാൽ 20 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ എത്ര പേരെ കൂടുതൽ നിയമിക്കണം?