Challenger App

No.1 PSC Learning App

1M+ Downloads
If Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?

A96 days

B128 days

C64 days

D118 days

Answer:

B. 128 days

Read Explanation:

Solution: Given: Rohit alone can complete one-fourth of a work in 32 days Formula used: (M × D × H/W = constant Where, M = number of person D = number of days H = number of hours W = work done Also, Work is directly proportional to days Calculation: One-fourth of the work can be completed in 32 days Then, Complete work will be completed in 32 × 4 = 128 days


Related Questions:

X, Y and Z can complete a piece of work in 46 days, 92 days and 23 days, respectively. X started the work. Y joined him after 7 days. If Z joined them after 8 days from the beginning, then for how many days did Y work?
A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in
എ, ബി എന്നീ രണ്ട് പൈപ്പുകൾക്ക് യഥാക്രമം 20, 30 മിനിറ്റുകൾ കൊണ്ട് ഒരു ടാങ്ക് നിറയ്ക്കാനാകും. രണ്ട് പൈപ്പുകളും ഒരുമിച്ച് ഉപയോഗിച്ചാൽ, ടാങ്ക് നിറയാൻ എത്ര സമയമെടുക്കും?
A can do a piece of work in 12 days and B can do it in 18 days. They work together for 2 days and then A leaves. How long will B take to finish the remaining work ?
One pipe fills a water tank 3 times faster than the other. If the two pipes together can fill the empty tank in 37 minutes, then how much time will the slower pipe alone take to fill the tank?