Ratul can do a piece of work in 24 days and Amal can do the same work in 32 days. They worked together for 8 days and then Amal left. How much time (in days ) will Ratul, working alone, take to complete the remaining work?

A10 days

B15 days

C12 days

D8 days

Answer:

A. 10 days

Read Explanation:

Let total work is 96 units ( LCM of 24 and 32) efficiency of Ratul = 96 /24 = 4 units The efficiency of Amal = 96 / 32 = 3 units So together do in one day 4 + 3 = 7 units they do in 8 days 7 × 8 = 56 units remaining, 96 - 56 = 40 units done by Ratul Ratul does the work in 40 / 4 = 10 days


Related Questions:

Abhay and Bharat can complete a certain piece of work in 9 and 11 days, respectively, They started to work together, and after 3 days, Bharat left. In how many days will Abhay complete the remaining work?
A Pipe can fill a tank in 10 hours. Due to leak in the bottom it fills the tank in 30 hours. If the tank is full, how much time will the leak take to empty it
One pipe fills a water tank 3 times faster than the other. If the two pipes together can fill the empty tank in 37 minutes, then how much time will the slower pipe alone take to fill the tank?
A can do a piece of work in 16 days and the same work can be done by B in 24 days, If they work individually on alternate days (i.e., on the first day A does the work and on the second day A was on leave and B done the second-day work and so on.) and A starts the work, then find the total days required to complete the work.
Two pipes are connected to a water tank. The first pipe can fill the tank in 10 minutes and the second pipe can empty it in 15 minutes. If both pipes opened simultaneously, then find the time in which the tank will be completely filled with water.