Slack represents the difference between the-

AProposed allowable time and the earliest expected time

BNormal allowable time and the latest expected time

CLatest allowable time and the normal expected time

DLatest allowable time and the earliest expected time

Answer:

D. Latest allowable time and the earliest expected time

Read Explanation:

Slack time is the difference between event times and represents the amount of time a task can be delayed before the project finish date is delayed. It is calculated as the difference between the latest allowable occurrence time (TL) and the earliest expected time (TE).


Related Questions:

The leaving basic variable in simplex method is the basic variable that
The _________________path within a network diagram is called critical path.

Consider the following statements regarding project management:Which of the given statements are INCORRECT?

  1. PERT is probabilistic and CPM is deterministic.
  2. In PERT, network slack on various events is calculated,
  3. In PERT, activity duration is normally distributed and project duration is beta distributed.
  4. The critical path of a network is the path that takes the shortest time.

    Consider the following statements in respect of PERT and CPM: Which of the statements are correct?

    1. PERT is event-oriented while CPM is activity-oriented.
    2. PERT is probabilistic while CPM is deterministic.
    3. Levelling and smoothing are the techniques related to resource scheduling in CPM.
      ____________________technology employs words like arrow diagram, nodes and float.