The primary objective of crashing in CPM is

ATo decrease cost

BTo increase cost

CTo decrease project duration

DTo optimise the path

Answer:

C. To decrease project duration

Read Explanation:

Project crashing is used to reduce project duration by investing more money. Only critical activities are considered and crashing is done on activities with lower cost slopes. The objective is to determine the optimum project duration with minimum cost. Steps include drawing a network diagram, selecting critical activity with minimum cost slope, reducing its duration, revising the diagram, and repeating until optimum duration is obtained.


Related Questions:

In linear programming problem when does feasibility change?
As per one of the assumptions of linear programming problem in operation research, objective function and constraints are assumed to be _____________
Linear programming
Negative slack occurs when -
The artificial activity which indicates that an activity following it cannot be started unless the preceding activity is complete, is known as-