Challenger App

No.1 PSC Learning App

1M+ Downloads
The artificial activity which indicates that an activity following it cannot be started unless the preceding activity is complete, is known as-

ADummy

BTotal float

CEvent

DFree float

Answer:

A. Dummy

Read Explanation:

Dummy activity is used to indicate that an activity following it cannot start unless the preceding activity is complete. It represents a logical precedence relationship and takes zero time and resources to perform. It is used to establish uniqueness in the network when two or more activities start from a single node and terminate at the same node


Related Questions:

Which of the following is NOT a direct cost?
________________is an operation research technique which aids the manager in making decisions involving the establishment of service facilities to meet irregular demands.
The cost of providing service in a queueing system increases with
______________ may be defined as any adjustment to the arrow diagram which becomes necessary owing to departure from the project schedule laid down earlier.
Any linear programming model must have all of the following properties EXCEPT: