The artificial activity which indicates that an activity following it cannot be started unless the preceding activity is complete, is known as-

ADummy

BTotal float

CEvent

DFree float

Answer:

A. Dummy

Read Explanation:

Dummy activity is used to indicate that an activity following it cannot start unless the preceding activity is complete. It represents a logical precedence relationship and takes zero time and resources to perform. It is used to establish uniqueness in the network when two or more activities start from a single node and terminate at the same node


Related Questions:

Which of the following is NOT a method of solving the transportation problem?
The mathematics technique for finding the best use of limited resources of a company in the optimum manner is known as

Consider the following statements regarding project management:Which of the given statements are INCORRECT?

  1. PERT is probabilistic and CPM is deterministic.
  2. In PERT, network slack on various events is calculated,
  3. In PERT, activity duration is normally distributed and project duration is beta distributed.
  4. The critical path of a network is the path that takes the shortest time.

    Consider the following statements regarding linear programming:Which of the given statements are correct?

    1. The graphical method cannot solve a linear programming problem with three variables and two constraints.
    2. In the Big-M method, when the artificial variable leaves the basis, its column can be deleted from the subsequent tables.
    3. When one constraint line comes parallel to the objective function line, LPP will have a degenerate solution.
      Which of the following is NOT a direct cost?