Which of the following is NOT a direct cost?

ARaw material consumed during production

BHire charges for tools and equipment

CRent, tax, and duties

DWages to laborers

Answer:

C. Rent, tax, and duties

Read Explanation:

Direct costs are expenses directly involved in completing a project, such as raw materials, equipment hire, and labor wages. Indirect costs are necessary but not directly involved. When a project is crashed to reduce the duration and cost, direct costs increase and indirect costs decrease. Rent, tax, and duties are not direct costs.